Quantitative risk analysis

Definition

In PMI usage, quantitative risk analysis examines numerically how the identified individual risks and other sources of uncertainty together affect the project objectives. Its focus is thus the overall project risk, for example the probability of meeting a finish date or a budget. Typical techniques are Monte Carlo simulation based on schedule and cost models, sensitivity analyses that show which risks influence the result most, and decision tree analysis. The results help to size reserves and to decide on responses to overall project risk. Because the technique requires data, tools and expertise, it is worthwhile mainly for large, complex or strategically important projects.

Equivalents in other frameworks

Concept Numerical assessment of overall risk · three frameworks reviewed

Equivalents of Quantitative risk analysis in other frameworks
FrameworkTerm thereRelationNote
generalQuantitative risk analysisequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

Broader term
Risk analysis
this term
Quantitative risk analysis

Distinction

The PMI name means the same as the cross-framework term quantitative risk analysis. While qualitative risk analysis ranks individual risks, quantitative analysis looks at their combined effect. The expected monetary value of a single risk is not yet a quantitative risk analysis in this sense.

In practice

For the construction of a wind farm there is a schedule with a finish date in October. The team enters three-point estimates for the key activities and models weather risks and delivery delays. The Monte Carlo simulation shows that October will be reached with only 35 percent probability, whereas a date in mid-December has 80 percent. The sensitivity analysis identifies crane availability as the largest driver; the project then secures a second crane by contract.

Frequently asked questions

Does every project need quantitative risk analysis?

No. For many projects qualitative analysis is sufficient. Quantitative analysis pays off when much is at stake, reliable data are available and decisions, for example on reserves or commitments, need a sound basis.

What does a Monte Carlo simulation deliver in a project?

A distribution of possible outcomes, such as finish dates or total costs, and thus the probability of achieving certain values. It does not show which outcome will occur but how likely the various outcomes are.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Quantitative risk analysis. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/

Short form

Quantitative risk analysis (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{quantitativeriskanalysispmi,
  title   = {Quantitative risk analysis},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/">
  <p>Numerical assessment of how individual risks and other uncertainties together are likely to affect the project's objectives.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/quantitative-risk-analysis-pmi/">Quantitative risk analysis</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.