Explicit policies

Definition

In the Kanban Guide, explicit policies are the visibly agreed rules by which work items pass through the individual states of a workflow from start to finish. They are among the minimum elements of the Definition of Workflow. Typical policies specify which conditions an item must meet before it moves to the next state, who may pull it, how urgent items are handled or which exceptions to the limit on work in progress are allowed. Explicit means that the rules are recorded in a way everyone involved can follow, instead of existing only in the heads of individuals. This makes decisions in the workflow predictable and allows them to be improved in a targeted way.

Equivalents in other frameworks

Concept Explicitly agreed working rules · two frameworks reviewed

Equivalents of Explicit policies in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKGround rulespartially overlappinggovern how work flows through the Kanban system, not behaviour within the team
generalTeam ground rulespartially overlappinggovern how work flows through the Kanban system, not behaviour within the team

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Explicit policies

Distinction

The Definition of Done in Scrum describes quality criteria for a finished result; explicit policies can contain such criteria but govern every transition in the workflow. Kanban University lists making policies explicit as a general practice in its own right. Team rules, by contrast, usually concern collaboration, not the flow of work.

In practice

On the board of a customer service team, the rule above the "Call back" column reads: a case is only pulled once the customer number and the request have been recorded, and complaints about direct debits take priority. When a new colleague passes on cases without a customer number, the others point him to the rule. In the monthly review, the team adds that cases are closed by e-mail after three unsuccessful call-back attempts.

Frequently asked questions

How detailed should policies be?

Concise enough to be read and followed in everyday work. Many teams write them directly on the board, next to the column they apply to.

May policies be changed at any time?

Yes. The Kanban Guide provides for improving the workflow continuously, without waiting for a fixed date. Changed policies should, however, again be recorded visibly for everyone.

Source and context

Reference
Kanban Guide 2025.5, Abschnitt Defining and Visualizing the Workflow
Edition
The Kanban Guide, May 2025
Cite this entry
APA

Explicit policies. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/explicit-policies/

Short form

Explicit policies (n.d.). PMDecoder, entry on Kanban Guide 2025.5, Abschnitt Defining and Visualizing the Workflow. https://pmdecoder.com/en/glossary/explicit-policies/ (retrieved 24 November 2026)

BibTeX
@misc{explicitpolicies,
  title   = {Explicit policies},
  note    = {PMDecoder, Kanban Guide 2025.5, Abschnitt Defining and Visualizing the Workflow},
  url     = {https://pmdecoder.com/en/glossary/explicit-policies/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/explicit-policies/">
  <p>Explicitly agreed rules for how work items move from one state to the next in a Kanban system; part of the Definition of Workflow</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/explicit-policies/">Explicit policies</a>, PMDecoder, Kanban Guide 2025.5, Abschnitt Defining and Visualizing the Workflow</footer>
</blockquote>

Found a mistake? Let us know, we check every report.