Gate
Definition
A gate is a point in the course of a project, fixed in advance and usually at the end of a phase, at which the undertaking is paused and assessed before funds for the next stretch are released. The review asks whether the results of the completed phase are available and meet the agreed criteria, whether the justification for the project still holds, and whether planning, risks and budget for the next phase are sound. The decision is taken by a body outside the project team that has the authority to do so. This entry refers to ISO/TR 21506:2018; in German, terms such as Phasenübergang or Entscheidungspunkt are also used.
Equivalents in other frameworks
Concept Decision point between project phases · six frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Phase gate | equivalent | — |
| PM² | Phase Gate | equivalent | — |
| Six Sigma | Tollgate | closely related | between the phases of the DMAIC cycle |
| PRINCE2 | Managing a stage boundary | partially overlapping | The Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board. |
| Scrum | — | no counterpart | continuation is decided continuously in the Sprint Review |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Gate
- Topic area
- Monitoring and control
Distinction
A milestone marks a point in time at which something is to have been achieved; a gate additionally requires a review and an explicit decision on how to proceed. The project phase is the stretch of work, the gate the transition between two such stretches. The PMI phase gate and the PM² Phase Gate are equivalent; the Six Sigma tollgate sits between the DMAIC phases. A quality gate in general usage often checks only the quality of results, not whether the undertaking as a whole should continue.
In practice
A medical device manufacturer is developing a new infusion pump in four phases. At the gate after the concept phase, the project manager presents the requirements specification, an updated cost estimate and the risk assessment to the steering committee. All criteria but one are met: the approval strategy has not yet been agreed with the notified body. The committee releases the design phase, but on condition that this agreement is reached within six weeks, and it holds back part of the budget until then.
Frequently asked questions
Who decides at a gate?
The decision is made by a party designated in advance with the necessary authority, for example the sponsor or a steering committee. The project manager prepares the basis for the decision and shows whether the agreed criteria have been met.
What happens if the criteria at a gate are not met?
The decision-makers can then require rework, let the project continue with conditions, ask for a new plan or stop the project. A gate at which termination is practically ruled out loses its purpose.
Is a gate the same as a milestone?
Not quite. A milestone marks a significant event in the schedule. A gate is a decision point involving review and approval. A gate often coincides with a milestone, such as the end of a phase.
Source and context
- Reference
- ISO/TR 21506:2018, 3.18
- Edition
- ISO/TR 21506:2018 · not the current edition
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Gate. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/gate/
Hain, D. (n.d.): Gate. PMDecoder, entry on ISO/TR 21506:2018, 3.18. https://pmdecoder.com/en/glossary/gate/ (retrieved 24 November 2026)
@misc{gate,
author = {Hain, Dennis},
title = {Gate},
note = {PMDecoder, ISO/TR 21506:2018, 3.18},
url = {https://pmdecoder.com/en/glossary/gate/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/gate/"> <p>Decision point between two project phases at which continuation, adjustment or termination is decided.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/gate/">Gate</a>, PMDecoder, ISO/TR 21506:2018, 3.18</footer> </blockquote>
Found a mistake? Let us know, we check every report.