Early start date

also: Early start · abbr. ES

Definition

The early start date, ES for short, results from the forward pass. For the first activity, it is the project start. For every further activity, it corresponds to the latest of the dates that its predecessors impose on it through their links and time intervals. The activity cannot logically start before this point in time, even if staff and materials were available.

Equivalents in other frameworks

Concept Earliest possible start of an activity · three frameworks reviewed

Equivalents of Early start date in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKEarly start dateequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Early start date

Distinction

The early start plus the duration gives the early finish date. The late start date indicates how far the start can be postponed without consequences for the project end; the difference between the two values is the total float. The start actually scheduled may lie later than the early start, for example because resources only become available then.

In practice

The installation of a facade has two predecessors: the building shell, which can be completed on 12 May, and the delivery of the facade elements, which has been promised for 19 May. The early start of the installation is therefore 19 May. When the facade contractor offers to start on the scaffolding as early as 15 May, the site management checks whether the scaffolding can be split off as a separate activity that depends only on the shell.

Frequently asked questions

How is the early start date calculated?

For finish-to-start relationships, as the largest early finish of all predecessors, each plus any time interval. Other types of relationship are taken into account accordingly.

Does an activity have to start on its early start date?

No. It may start later, as long as it does not exceed its late start date.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Early start date. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/early-start-date/

Short form

Hain, D. (n.d.): Early start date. PMDecoder. https://pmdecoder.com/en/glossary/early-start-date/ (retrieved 24 November 2026)

BibTeX
@misc{earlystartdate,
  author  = {Hain, Dennis},
  title   = {Early start date},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/early-start-date/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/early-start-date/">
  <p>Earliest possible point in time at which an activity can start if all predecessors are completed on schedule</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/early-start-date/">Early start date</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.