Tailor to suit the project

Definition

The principle tailor to suit the project states that PRINCE2 should not be applied mechanically. Practices, processes, roles and management products are adapted to fit the size, complexity, importance, risk, team and context of the project. Roles can be combined, processes simplified and documents kept shorter or in a different form, for example as a board in a tool rather than as a report. The principles themselves are not negotiable: if one of them is missing, the project is not considered a PRINCE2 project. How the method is tailored is agreed and documented during initiation.

Equivalents in other frameworks

Concept Adapting the method to the undertaking · one framework reviewed

Equivalents of Tailor to suit the project in other frameworks
FrameworkTerm thereRelationNote
PM²Tailoringclosely relatedIn PRINCE2 a mandatory principle; the seven principles themselves may not be dropped.

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Tailor to suit the project

Distinction

Tailoring in PM² and in PMI publications has the same aim of adapting the method to its use. PRINCE2 makes adaptation explicitly a principle and therefore mandatory. Tailoring does not mean leaving things out: a task may be simplified, but its purpose must still be met.

In practice

A foundation runs a small project with four people to digitize its archive. The managing director acts as Executive and at the same time as Senior User, progress reports are sent as a short email, and plans are kept in a simple spreadsheet. The team nevertheless keeps the end-of-stage decisions and the review of the business justification.

Frequently asked questions

What must not be dropped when tailoring PRINCE2?

The seven principles. Everything else, from roles and processes to documents, can be tailored as long as its purpose is preserved.

Who decides on tailoring?

The project manager prepares proposals and the Project Board approves them. Requirements of the commissioning organization, such as its own project handbook, are taken into account.

Source and context

Reference
PRINCE2 7, Grundprinzipien
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Tailor to suit the project. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/tailor-to-suit-the-project/

Short form

Hain, D. (n.d.): Tailor to suit the project. PMDecoder, entry on PRINCE2 7, Grundprinzipien. https://pmdecoder.com/en/glossary/tailor-to-suit-the-project/ (retrieved 24 November 2026)

BibTeX
@misc{tailortosuittheproject,
  author  = {Hain, Dennis},
  title   = {Tailor to suit the project},
  note    = {PMDecoder, PRINCE2 7, Grundprinzipien},
  url     = {https://pmdecoder.com/en/glossary/tailor-to-suit-the-project/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/tailor-to-suit-the-project/">
  <p>PRINCE2 principle: the method is adapted to the size, risk, context and approach of each project without abandoning the principles.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/tailor-to-suit-the-project/">Tailor to suit the project</a>, PMDecoder, PRINCE2 7, Grundprinzipien</footer>
</blockquote>

Found a mistake? Let us know, we check every report.