Start after the predecessor finishes

Concept · 2 of 10 frameworks name this concept

The most common logical relationship: an activity can start only when its predecessor has finished, such as painting only after the plastering is complete.

ConceptStart after the predecessor finishesTopic area Network planning
Preferred term
cross-frameworkFinish-to-start relationshipalso FS
equivalent
PMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Finish-to-start
Concordance of the concept “Start after the predecessor finishes”. The preferred term is the designation under which the glossary lists the concept.