Forward pass
also: Forward pass calculation
Definition
The forward pass begins at the start activity and works step by step through the network schedule. Each activity receives an early start date, derived from the dates of its predecessors and any time intervals, and an early finish date calculated as start plus duration. Where several predecessors converge, the one that finishes last determines the start. At the end activity, the result is the earliest possible project completion.
Equivalents in other frameworks
Concept Calculation of earliest dates · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Forward pass | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Forward pass
- Topic area
- Network planning
Distinction
The backward pass works the other way round, from the project end to the start, and provides the latest dates. Only the two calculations together yield float and the critical path. The forward pass therefore answers when the project can be finished at the earliest, but not which activities are decisive for this.
In practice
A project starts on day 0 with activity A, which takes four days. A is followed by B with six days and C with three days; D, with two days, needs both B and C. The forward pass shows that A finishes on day 4 at the earliest, B on day 10 and C on day 7. D has to wait for B, so it starts on day 10 at the earliest and finishes on day 12. The project can therefore be completed after twelve days at the earliest.
Frequently asked questions
Why does the predecessor that finishes last determine the start?
Because a successor can only start once all its predecessors are complete. The decisive one is therefore the predecessor that finishes last.
Do you count from day 0 or from day 1?
Both are common. What matters is to apply one counting convention consistently, because otherwise dates shift by one day.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Forward pass. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/forward-pass/
Hain, D. (n.d.): Forward pass. PMDecoder. https://pmdecoder.com/en/glossary/forward-pass/ (retrieved 24 November 2026)
@misc{forwardpass,
author = {Hain, Dennis},
title = {Forward pass},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/forward-pass/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/forward-pass/"> <p>Calculation of the earliest possible start and finish dates of all activities, working from the project start along the dependencies</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/forward-pass/">Forward pass</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.