Project management office
Definition
In PMI usage, a project management office (PMO) is an organizational unit that standardizes the governance processes associated with projects and makes it easier to share resources, methods, tools and techniques. Its tasks range from templates, training and coaching through collecting project data and reporting to managing projects directly. PMI literature often distinguishes PMOs by their degree of influence: supportive, controlling or directive. A PMO may be set up for a single large project, a program, a portfolio or the whole organization.
Equivalents in other frameworks
Concept Project management support function · five frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Project management office | equivalent | — |
| PRINCE2 | Project Support | closely related | A role within a single project, not a permanent unit; a project office may fill it. |
| PM² | Project Support Team | partially overlapping | supports only one project with administration, reporting and documentation, without overarching responsibility for methods |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Project management office
- Topic area
- Project organization
Distinction
The term corresponds to the project management office in the standard. The project support team in PM² is narrower and mainly provides administrative support to a single project. A PMO does not replace the project manager: responsibility for project objectives stays with the project manager, while the PMO provides the framework, methods and overview. In a portfolio context it often supports portfolio management.
In practice
An energy utility carries out around forty projects a year, which until now were planned with different templates. It sets up a PMO that provides uniform templates for the project charter and status report, onboards new project managers and produces a monthly overview of the schedule, cost and risks of all projects for senior management. After a year, the PMO also takes over the preparation of prioritization rounds.
Frequently asked questions
What types of PMO are there?
A common distinction is by influence: a supportive PMO provides templates and knowledge, a controlling PMO requires compliance with standards and checks it, and a directive PMO manages projects itself by providing the project managers.
How is the success of a PMO measured?
By its contribution to the organization's objectives, for example more reliable forecasts, fewer cancelled projects or faster decisions. The number of reports produced is not a measure of success.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Project management office. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-management-office-pmi/
Project management office (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/project-management-office-pmi/ (retrieved 24 November 2026)
@misc{projectmanagementofficepmi,
title = {Project management office},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/project-management-office-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-management-office-pmi/"> <p>Organizational unit that harmonizes project management methods and governance across an organization and supports projects in applying them.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-management-office-pmi/">Project management office</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.