Project plan
Definition
In the sense of ISO 21506, the project plan is not merely a schedule but the document that sets out what a project is to adhere to. On the one hand, it describes the technical basis, such as requirements, specifications and deliverables; on the other, the baselines for management and control, such as scope, schedule, cost, resources, risks and communication. Once approved, it becomes the project's yardstick and is only changed through a controlled change procedure.
Equivalents in other frameworks
Concept Comprehensive project management plan · five frameworks reviewed · two false friends
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | Project Plan | false friendno overlap | Despite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level. |
| general | Project plan | false friendno overlap | The project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery. |
| PMI / PMBOK | Project management plan | equivalent | — |
| PRINCE2 | Project Initiation Documentation | closely related | Collection of management products that also includes the business case; its approval authorizes the project. |
| PM² | Project Handbook | closely related | contains the management approach and management plans; work breakdown, effort, cost and schedule are in the project work plan |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Project plan
- Topic area
- Planning and project structure
Distinction
In German usage, Projektplan often means only the schedule, for example a bar chart. The project plan of the standard is more comprehensive and largely corresponds to the project management plan of the PMBOK Guide. Programmes have a corresponding document in the programme plan.
In practice
For the modernization of a railway signal box, the project manager presents a project plan in two parts to the steering committee. The technical part contains the system requirements, the list of deliverables and the test specification. The management part contains the work breakdown structure, schedule, budget, resource plan, risk register and communication plan. On approval, both become the baseline. When the test specification later has to be changed, this goes through a change request so that the technical status remains traceable.
Frequently asked questions
Is the project plan the same as the schedule?
Not according to ISO 21506. The schedule is only one part of it; the project plan also covers the technical basis and the other project management baselines.
Does the project plan have to be a single document?
No. It can consist of several subsidiary plans that are brought together in one place and approved together. What matters is that it is clear which versions apply.
Source and context
- Reference
- ISO 21506:2024, 3.68
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Project plan. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-plan-iso/
Hain, D. (n.d.): Project plan. PMDecoder, entry on ISO 21506:2024, 3.68. https://pmdecoder.com/en/glossary/project-plan-iso/ (retrieved 24 November 2026)
@misc{projectplaniso,
author = {Hain, Dennis},
title = {Project plan},
note = {PMDecoder, ISO 21506:2024, 3.68},
url = {https://pmdecoder.com/en/glossary/project-plan-iso/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-plan-iso/"> <p>Under ISO 21506, the binding document that brings together a project's technical baselines and its management baselines.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-plan-iso/">Project plan</a>, PMDecoder, ISO 21506:2024, 3.68</footer> </blockquote>
Found a mistake? Let us know, we check every report.