Estimate to complete
Definition
In PMI usage, estimate to complete (ETC) is the cost expected to be needed to finish the remaining work of a project or of part of it. The figure looks forward: it starts at the status date of the measurement and ends at completion. Added to the actual cost already incurred, it gives the expected total cost, the estimate at completion. ETC can be determined either by a fresh bottom-up estimate of the remaining work or by calculation from earned value indicators, for example by dividing the budget not yet earned by the cost performance index.
Equivalents in other frameworks
Concept Expected cost of the remaining work · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Estimate to complete | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Estimate to complete
- Topic area
- Monitoring and control
Distinction
The term corresponds to the ISO 21506 term estimate to complete; the PMI usage is widespread in English-speaking practice and in PMI certification. Estimate at completion covers the entire expected cost including the past, ETC only the remainder. ETC differs from the original budget at completion in that it reflects current knowledge and the cost efficiency achieved so far.
In practice
A software project has a budget of 800,000 euros. At month end, work worth 300,000 euros has been performed at a cost of 360,000 euros; the cost performance index is about 0.83. By calculation, the ETC for the remaining 500,000 euros of budget is roughly 600,000 euros. The project manager also asks the teams to re-estimate the open work packages. Their result of 540,000 euros goes into the status report to the sponsor, together with the reasoning behind it.
Frequently asked questions
When is a re-estimate better than the formula?
When conditions have changed, for example through new suppliers, changed requirements or resolved start-up problems. The formula extrapolates past efficiency and therefore fits best when the causes of earlier variances are still at work.
Can ETC be lower than the remaining budget?
Yes. If a project works more cost-efficiently than planned or work is dropped, ETC falls below the budget not yet earned. The difference should still be justified so that it does not rest on overly optimistic assumptions.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Estimate to complete. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/estimate-to-complete-pmi/
Estimate to complete (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/estimate-to-complete-pmi/ (retrieved 24 November 2026)
@misc{estimatetocompletepmi,
title = {Estimate to complete},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/estimate-to-complete-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/estimate-to-complete-pmi/"> <p>Forecast of the costs still to come from the status date onwards until all outstanding project work is done.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/estimate-to-complete-pmi/">Estimate to complete</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.