Cost of quality
Definition
In PMI terms, cost of quality (COQ) brings together all quality-related costs incurred over the life cycle of a product. PMI distinguishes two groups. Costs of conformance arise from preventing defects and appraising results, for example training, process documentation, testing and inspection. Costs of nonconformance arise from failures, either internally before handover, such as rework and scrap, or externally after handover, such as warranty work, recalls and lost customers. The underlying idea is that investment in prevention usually lowers total cost.
Equivalents in other frameworks
Concept Costs of prevention, appraisal and failure · four frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Cost of quality | equivalent | — |
| Six Sigma | Cost of Poor Quality | partially overlapping | Covers only the cost of poor quality, but explicitly includes hidden follow-on costs; prevention costs are not part of it. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
All designations of this concept side by side
Comparisons
Classification
- this term
- Cost of quality
- Topic area
- Quality
Distinction
The term corresponds to the cross-framework concept of quality costs. It is broader than the project budget because it also includes costs after the project ends, such as warranty work at the customer. It shares the life-cycle view with total cost of ownership but is limited to quality-related costs.
In practice
A project for railway control software compares two options: additional automated tests costing EUR 60,000 or the existing test level. An analysis of earlier projects shows that defects found in the field caused several times that amount in fixes and contractual penalties. The team opts for the additional tests.
Frequently asked questions
Why include costs after the project ends?
Many consequences of poor quality only appear in operation. Looking only at project costs makes it tempting to save on prevention and shift higher costs to users.
Is higher quality always more expensive?
Not necessarily. More effort on prevention and appraisal can reduce failure costs by more than it costs itself. Cost of quality makes this relationship visible.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Cost of quality. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/cost-of-quality-pmi/
Cost of quality (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/cost-of-quality-pmi/ (retrieved 24 November 2026)
@misc{costofqualitypmi,
title = {Cost of quality},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/cost-of-quality-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/cost-of-quality-pmi/"> <p>Sum of the expenses for preventing defects, for inspection and for the consequences of failures over the whole life of a product.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/cost-of-quality-pmi/">Cost of quality</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.