Deliverable

Definition

A deliverable is any clearly described result that a project or part of it must produce. It can be a product, a facility, a document such as a concept or test report, a software release or a service provided, such as training. Deliverables can be verified and form the basis for acceptance, progress measurement and often payments.

Equivalents in other frameworks

Concept Verifiable project result · two frameworks reviewed

Equivalents of Deliverable in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKDeliverableequivalent—
ScrumIncrementpartially overlappingusable step towards the Product Goal that includes all previous Increments; not every deliverable is an Increment

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Deliverable

Distinction

A deliverable is a result, an activity the work that leads to it. A milestone marks a point in time by which a deliverable often has to be available, but is not itself a result. A distinction is made between external deliverables for the client and internal ones that are only needed within the project, such as a test concept.

In practice

In a contract for a website redesign, the agency lists twelve deliverables, including a design concept, a prototype, the finished website and editorial training. For each one, the contract describes in what form it is handed over and how acceptance is determined. When the client also expects a style guide, it can quickly be shown that this was not agreed; both sides negotiate it as an additional order.

Frequently asked questions

How do you describe a deliverable well?

With its name, content, form, quality characteristics, date, recipient and the criteria by which it will be accepted.

Are project management documents deliverables too?

Yes, if they have been agreed, such as a final report. Many contracts, however, treat them as internal results without separate acceptance.

Source and context

Reference
ISO 21506:2024, 3.20
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Deliverable. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/deliverable/

Short form

Hain, D. (n.d.): Deliverable. PMDecoder, entry on ISO 21506:2024, 3.20. https://pmdecoder.com/en/glossary/deliverable/ (retrieved 24 November 2026)

BibTeX
@misc{deliverable,
  author  = {Hain, Dennis},
  title   = {Deliverable},
  note    = {PMDecoder, ISO 21506:2024, 3.20},
  url     = {https://pmdecoder.com/en/glossary/deliverable/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/deliverable/">
  <p>Verifiable result that is produced in a project and handed over to the client, users or subsequent work.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/deliverable/">Deliverable</a>, PMDecoder, ISO 21506:2024, 3.20</footer>
</blockquote>

Found a mistake? Let us know, we check every report.