Project management office

abbr. PMO

Definition

A project management office is a permanent function or unit, or one set up for a major undertaking, that supports project work across the organization. Depending on its remit, it provides templates and methods, trains project managers, collects status reports, maintains key figures and prepares decisions for portfolio management. In some organizations it also runs projects itself.

Equivalents in other frameworks

Concept Project management support function · five frameworks reviewed

Equivalents of Project management office in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKProject management officeequivalent—
PRINCE2Project Supportclosely relatedA role within a single project, not a permanent unit; a project office may fill it.
PM²Project Support Teampartially overlappingsupports only one project with administration, reporting and documentation, without overarching responsibility for methods
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Project management office

Distinction

Broadly, there are three types: supportive, with templates and advice; controlling, with binding standards and reviews; and directive, with its own project responsibility. A project office in the narrower sense, by contrast, provides administrative support to a single project only. A programme management office performs comparable tasks for a programme made up of several related projects.

In practice

A state authority sets up a project management office after it turns out that nobody knew how many IT projects were running at the same time. In the first year, the office records all undertakings in a list, introduces a standard one-page report and briefs the authority's management every quarter. Only then are method standards made binding, so that the office is not perceived as a mere control body.

Frequently asked questions

Who does a project management office report to?

Usually to executive management, a board member or the division responsible for the project portfolio. A high-level reporting line strengthens its influence.

Why do project management offices fail?

Often because they demand forms without noticeably helping the projects. Value is created when reports lead to decisions and templates save work.

Source and context

Reference
ISO 21506:2024, 3.66
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Project management office. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-management-office/

Short form

Hain, D. (n.d.): Project management office. PMDecoder, entry on ISO 21506:2024, 3.66. https://pmdecoder.com/en/glossary/project-management-office/ (retrieved 24 November 2026)

BibTeX
@misc{projectmanagementoffice,
  author  = {Hain, Dennis},
  title   = {Project management office},
  note    = {PMDecoder, ISO 21506:2024, 3.66},
  url     = {https://pmdecoder.com/en/glossary/project-management-office/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/project-management-office/">
  <p>Function or organizational unit that makes managing projects easier, for example through methods, support and an overview for senior management.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-management-office/">Project management office</a>, PMDecoder, ISO 21506:2024, 3.66</footer>
</blockquote>

Found a mistake? Let us know, we check every report.