Project Plan

Definition

In PRINCE2, the project plan is the plan for the entire project. At a high level it shows which major products are created, into which management stages the project is divided, which milestones there are and which time, resources and costs are provided for. It also contains the project tolerances, assumptions, dependencies and the controls used to monitor progress. It is created during initiation, is part of the project initiation documentation and serves the project board as a baseline for comparison. It is updated with the actual status at each stage boundary.

Equivalents in other frameworks

Concept Comprehensive project management plan · five frameworks reviewed · five false friends

Equivalents of Project Plan in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Project management plan no entry yetfalse friendno overlapDespite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level.
ISO 21506Project planfalse friendno overlapDespite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level.
PMI / PMBOKProject management planfalse friendno overlapDespite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level.
PM²Project Handbookfalse friendno overlapDespite the name, not the comprehensive plan: the PRINCE2 project plan is only one part of the project initiation documentation and covers products, stages, dates and costs at a high level.
generalProject planfalse friendno overlapThe project management plan comprises all subsidiary plans, including scope, schedule, cost, quality, risk and communication. Anyone who says “Projektplan” in German almost always means just the schedule. In international projects, this confusion regularly leads to misunderstandings about the scope of delivery.

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Project Plan

Distinction

The name is misleading: the PRINCE2 project plan is not the comprehensive PMI project management plan, nor the project plan under ISO 21506 that bundles all baselines. In PRINCE2 that role is taken by the project initiation documentation, of which the project plan is one part. Nor is it merely a schedule, as “project plan” is often understood, because it also covers products, costs and controls.

In practice

For introducing a new payroll system, the project plan shows four stages: initiation, design, build and test, and roll-out. For each stage the major products, costs and planned end dates are given, together with a tolerance of five per cent on the total budget. The individual tasks of the design stage are not in the project plan but in the stage plan for that stage.

Frequently asked questions

How detailed is a project plan?

Broad enough to remain reliable for the duration of the whole project. The details are in the stage plans, each of which is produced shortly before the stage concerned.

Who approves the project plan?

The project board, as part of the project initiation documentation. The project manager also submits updates at stage boundaries to the board.

Source and context

Reference
PRINCE2 7, Praktik Pläne
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Project Plan. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-plan-prince2/

Short form

Hain, D. (n.d.): Project Plan. PMDecoder, entry on PRINCE2 7, Praktik Pläne. https://pmdecoder.com/en/glossary/project-plan-prince2/ (retrieved 24 November 2026)

BibTeX
@misc{projectplanprince2,
  author  = {Hain, Dennis},
  title   = {Project Plan},
  note    = {PMDecoder, PRINCE2 7, Praktik Pläne},
  url     = {https://pmdecoder.com/en/glossary/project-plan-prince2/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/project-plan-prince2/">
  <p>PRINCE2 plan showing for the whole project which major products are delivered when, with which resources and at what cost.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-plan-prince2/">Project Plan</a>, PMDecoder, PRINCE2 7, Praktik Pläne</footer>
</blockquote>

Found a mistake? Let us know, we check every report.