Code of accounts

Definition

In PMI usage, the code of accounts is a numbering scheme that gives every element of the work breakdown structure a unique identifier. Hierarchical identifiers such as 1, 1.2 and 1.2.3 are common, showing the position of a component within the structure. This identifier makes it possible to relate work packages, costs, dates and responsibilities to one another and to bring together information from different plans and systems. The identifier is also recorded in the WBS dictionary.

Equivalents in other frameworks

Concept Identifier of work breakdown structure elements · one framework reviewed

Equivalents of Code of accounts in other frameworks
FrameworkTerm thereRelationNote
generalWBS codeclosely relateddenotes the entire numbering system, the WBS code the individual identifier

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Code of accounts

Distinction

The cross-framework WBS code denotes the individual identifier of a component, whereas PMI’s code of accounts tends to mean the system of these identifiers, hence the close but not identical mapping. It must be distinguished from the chart of accounts, which structures the organization’s financial accounting rather than the project content.

In practice

A construction project divides its scope into shell construction, interior finishing and external works, numbered 1, 2 and 3. Interior finishing is broken down into 2.1 electrical, 2.2 plumbing and 2.3 plastering. Accounting records every invoice with the identifier of the component concerned. The project manager can therefore see at any time that 2.2 has already used 90 percent of its budget although the work is only half finished.

Frequently asked questions

Does the code of accounts have to match the accounting numbers?

Not necessarily, but a link helps. Many organizations record the associated cost centre or cost type for each component of the structure so that actual costs can be assigned without extra work.

What happens to the identifiers when the structure changes?

Identifiers already assigned should remain stable so that reports stay comparable. New components get new numbers, and dropped ones are marked as deleted rather than having their number reused.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Code of accounts. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/code-of-accounts/

Short form

Code of accounts (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/code-of-accounts/ (retrieved 24 November 2026)

BibTeX
@misc{codeofaccounts,
  title   = {Code of accounts},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/code-of-accounts/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/code-of-accounts/">
  <p>Numbering scheme that assigns every WBS element a distinct identifier such as 1.2.3, making costs and dates traceable to it.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/code-of-accounts/">Code of accounts</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.