Latest allowable finish of an activity
The latest point in time by which an activity must be finished so that neither successors nor the project end are delayed; result of the backward pass.
Preferred term
equivalent
PMI / PMBOK Guide · PMI Lexicon of Project Management Terms 4.0 (2024)Late finish date