Tolerance (PRINCE2)
Definition
Tolerance in PRINCE2 is the permitted margin around a planned target, such as a budget or a date. Within this margin the responsible level may act on its own; only when the forecast threatens to leave it does the level above have to be involved. Tolerances are set for various aspects, for example time, cost, scope, quality, benefits and risk. They are delegated in steps: by the commissioning organization for the project, by the Project Board for stages and by the Project Manager for work packages. Tolerances are therefore the tool through which management by exception is put into practice.
Equivalents in other frameworks
Concept Permitted margin for deviations · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Variance threshold | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Tolerance (PRINCE2)
- Topic area
- Monitoring and control
Distinction
The variance threshold in ISO 21506 describes the same idea of a defined limit. Risk tolerance, by contrast, refers only to the willingness to take risks. A variance is the actual difference between plan and actual; tolerance determines how large a variance may be before it must be escalated. A reserve or buffer is planned time or money, not a decision limit.
In practice
For the fit-out stage of an office refurbishment, the Project Board sets a budget of 1.2 million euros with plus ten and minus five per cent and a completion date with three weeks of leeway. No scope tolerance is given: all agreed rooms must be finished. The Project Manager handles a seven per cent cost increase himself.
Frequently asked questions
Can a tolerance be zero?
Yes. It means that any deviation in that aspect must be referred to the Project Board, for example when a statutory deadline cannot be moved.
Why is there a tolerance below the target as well?
Because significantly lower costs or much earlier completion can also point to planning errors or missing scope. The level above should be made aware of this.
Source and context
- Reference
- PRINCE2 7, Praktik Fortschritt
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Tolerance (PRINCE2). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/tolerance-prince2/
Hain, D. (n.d.): Tolerance (PRINCE2). PMDecoder, entry on PRINCE2 7, Praktik Fortschritt. https://pmdecoder.com/en/glossary/tolerance-prince2/ (retrieved 24 November 2026)
@misc{toleranceprince2,
author = {Hain, Dennis},
title = {Tolerance (PRINCE2)},
note = {PMDecoder, PRINCE2 7, Praktik Fortschritt},
url = {https://pmdecoder.com/en/glossary/tolerance-prince2/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/tolerance-prince2/"> <p>In PRINCE2, the permitted deviation above or below a planned target within which a level may decide without referring to the level above.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/tolerance-prince2/">Tolerance (PRINCE2)</a>, PMDecoder, PRINCE2 7, Praktik Fortschritt</footer> </blockquote>
Found a mistake? Let us know, we check every report.