Management reserve
abbr. MR
Definition
The management reserve covers what could not be foreseen during planning but still belongs to the agreed scope, such as unexpected rework or tasks that no work package allowed for. It is deliberately not distributed to control accounts and is therefore not included in performance measurement. If part of it is needed, management releases that amount; it is then assigned to a control account and increases the baseline.
Equivalents in other frameworks
Concept Reserve for unforeseen work · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Management reserve | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Management reserve
- Topic area
- Risks and opportunities
Distinction
The risk contingency reserve is planned for identified risks and usually belongs to the baseline, whereas the management reserve is intended for the unknown and sits outside it. Neither is meant for changes in scope: additional work requires an approved change request and, as a rule, additional budget.
In practice
An energy utility approves 18 million euros for building a substation, of which 16.9 million form the performance measurement baseline and 1.1 million the management reserve. During excavation, the contractor comes across an undocumented old pipeline whose relocation costs 240,000 euros. The project manager requests a release from the management reserve, the steering committee agrees, and the amount is assigned to the control account for civil works.
Frequently asked questions
Who may use the management reserve?
As a rule not the project manager alone but a higher authority such as the client, the sponsor or the steering committee. The authority to release it is defined in advance.
How large should the management reserve be?
There is no fixed rate. It depends on how novel and complex the undertaking is and on experience from comparable projects, and it is often set as a percentage of the budget.
Source and context
- Reference
- ISO 21506:2024, 3.36
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Management reserve. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/management-reserve/
Hain, D. (n.d.): Management reserve. PMDecoder, entry on ISO 21506:2024, 3.36. https://pmdecoder.com/en/glossary/management-reserve/ (retrieved 24 November 2026)
@misc{managementreserve,
author = {Hain, Dennis},
title = {Management reserve},
note = {PMDecoder, ISO 21506:2024, 3.36},
url = {https://pmdecoder.com/en/glossary/management-reserve/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/management-reserve/"> <p>Portion of the budget held back for unforeseeable work within the agreed scope, released by management and not part of the measurement baseline.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/management-reserve/">Management reserve</a>, PMDecoder, ISO 21506:2024, 3.36</footer> </blockquote>
Found a mistake? Let us know, we check every report.