Fast tracking
Definition
In PMI usage, fast tracking is a schedule compression technique that lets activities or phases which would usually follow one another run in parallel for part of their duration. A successor activity therefore starts before its predecessor is fully complete. This is only possible where the sequence is not mandatory, that is, with discretionary dependencies, and where overlapping actually brings the project end forward, that is, on the critical path. Fast tracking costs little extra at first but increases the risk of rework because work builds on provisional results.
Equivalents in other frameworks
Concept Shortening through parallel work · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Fast tracking | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Schedule compression
- this term
- Fast tracking
- Topic area
- Scheduling
Distinction
The cross-framework entry on fast tracking describes the same technique; in PMI terminology it is, like crashing, a form of schedule compression. Crashing shortens the schedule with additional resources and mainly increases cost, whereas fast tracking shortens it through overlap and mainly increases risk.
In practice
In developing an advertising campaign, production of the commercials was supposed to start only after the script had been fully approved. To keep to the launch date, the production company starts casting and location scouting as soon as the basic idea has been approved. This saves three weeks. When the client drops a scene, a location already booked is no longer needed; the team knowingly accepts the cancellation costs.
Frequently asked questions
Which activities are suitable for fast tracking?
Those on the critical path whose sequence is not technically or legally mandatory and where follow-on work can usefully begin with provisional results.
How can the risk be limited?
By overlapping only part of the duration, exchanging interim results early and agreeing in advance which rework is acceptable if the predecessor work changes.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Fast tracking. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/fast-tracking-pmi/
Fast tracking (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/fast-tracking-pmi/ (retrieved 24 November 2026)
@misc{fasttrackingpmi,
title = {Fast tracking},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/fast-tracking-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/fast-tracking-pmi/"> <p>Shortening the schedule by letting activities that would normally run one after another overlap in time; saves time but raises the risk of rework.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/fast-tracking-pmi/">Fast tracking</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.