Phase Gate
Definition
In PM², a Phase Gate is a checkpoint between two phases of the life cycle. Before the project continues, certain participants, usually the Project Manager, the Project Owner and the Project Steering Committee, check whether the objectives of the completed phase have been achieved. PM² has three such gates: Ready for Planning at the end of initiation, Ready for Executing at the end of planning and Ready for Closing at the end of execution. For each phase there is a phase-exit review checklist that the Project Manager uses to prepare the assessment. The gates support good governance and a controlled course of the project.
Equivalents in other frameworks
Concept Decision point between project phases · six frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Gate | equivalent | — |
| PMI / PMBOK | Phase gate | equivalent | — |
| Six Sigma | Tollgate | closely related | between the phases of the DMAIC cycle |
| PRINCE2 | Managing a stage boundary | partially overlapping | The Project Manager’s preparation of the decision point; the decision itself is taken by the Project Board. |
| Scrum | — | no counterpart | continuation is decided continuously in the Sprint Review |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Phase Gate
- Narrower terms
- Ready for ClosingReady for ExecutingReady for Planning
- Topic area
- Monitoring and control
Distinction
The PM² Phase Gate corresponds to the gate in ISO 21506 and to the phase gate in the PMBOK Guide. A milestone, by contrast, only marks a date and need not be linked to an approval.
In practice
Before the move into execution, the Project Manager of an archiving project goes through the phase-exit review checklist and finds that the Transition Plan is still missing. He postpones the presentation to the Project Steering Committee by three weeks rather than asking for conditional approval.
Frequently asked questions
How many Phase Gates does a PM² project have?
Three: Ready for Planning, Ready for Executing and Ready for Closing. After the Closing Phase, the project ends with the final approval by the Project Owner.
Are Phase Gates mandatory in PM²?
The guide recommends a review and approval before each transition. How formal it is can be adapted to the size and importance of the project.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 3.2.6
- Edition
- PM² Guide 3.1
Cite this entry
Phase Gate. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/phase-gate/
Phase Gate (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 3.2.6. https://pmdecoder.com/en/glossary/phase-gate/ (retrieved 24 November 2026)
@misc{phasegate,
title = {Phase Gate},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 3.2.6},
url = {https://pmdecoder.com/en/glossary/phase-gate/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/phase-gate/"> <p>Approval point at the end of a PM² phase at which it is checked whether the project may move on to the next phase</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/phase-gate/">Phase Gate</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 3.2.6</footer> </blockquote>
Found a mistake? Let us know, we check every report.