Finish-to-start

Definition

Finish-to-start, FS for short, is the most common of the four logical relationships in a schedule. It states that the successor cannot start before the predecessor is completed. It thus represents the simple sequence “first one thing, then the other” that dominates most workflows. Many scheduling tools use it as the default when two activities are linked. A lag can be used to plan a waiting period between finish and start, a lead to bring the successor's start forward.

Equivalents in other frameworks

Concept Start after the predecessor finishes · three frameworks reviewed

Equivalents of Finish-to-start in other frameworks
FrameworkTerm thereRelationNote
generalFinish-to-start relationshipequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Finish-to-start

Distinction

Finish-to-start corresponds to the German Normalfolge in network planning. With start-to-start and finish-to-finish, activities may overlap; with finish-to-start and no lead, they may not. When a schedule is shortened by fast tracking, finish-to-start relationships are often replaced by overlaps or other relationship types.

In practice

When a medical practice moves to new premises, installation of the treatment chairs can only start once the floor covering has been laid. The project manager links the two activities with finish-to-start. Because the adhesive needs two days to cure before it can bear loads, she adds a lag of two days. If the flooring is delayed, the scheduling tool moves the installation automatically.

Frequently asked questions

Why is finish-to-start the most common relationship type?

Because most work steps build on a finished result. The relationship is also easy to understand and makes the plan clear to everyone involved.

Should only finish-to-start be used?

Not necessarily. Where activities genuinely overlap, another relationship type represents the workflow more accurately. Linking everything with finish-to-start often produces a longer plan than needed.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Finish-to-start. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/finish-to-start/

Short form

Finish-to-start (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/finish-to-start/ (retrieved 24 November 2026)

BibTeX
@misc{finishtostart,
  title   = {Finish-to-start},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/finish-to-start/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/finish-to-start/">
  <p>Most common schedule link: the successor can begin at the earliest once the predecessor is complete, so one thing follows the other.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/finish-to-start/">Finish-to-start</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.