Sprint

Definition

In Scrum, the Sprint is the recurring work cycle in which ideas are turned into usable results. Every Sprint has a fixed length of one month or less, and the next Sprint begins as soon as the previous one ends. The four other events lie entirely within it, from Sprint Planning and the Daily Scrums through to the Review and Retrospective. While the Sprint is running, the Sprint Goal is protected, quality is not lowered, and the Product Backlog continues to be refined as needed. As the team learns more, it can renegotiate the scope of work with the Product Owner. Only the Product Owner may cancel a Sprint, and only when its Sprint Goal is no longer meaningful.

Equivalents in other frameworks

Concept Time-boxed work cycle · three frameworks reviewed

Equivalents of Sprint in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKIterationclosely relatedone month at most, with a Sprint Goal and fixed events; contains all the work up to the Increment
generalIterationclosely relatedone month at most, with a Sprint Goal and fixed events; contains all the work up to the Increment
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

Broader term
Scrum Event
this term
Sprint

Distinction

A Sprint is an iteration with fixed rules: a constant length, one Sprint Goal and four events within it. A project phase, by contrast, usually has its own duration and ends with an approval. The Scrum Guide compares each Sprint to a short project; however, continuation is not decided at a gate but discussed in the Sprint Review on the basis of the result.

In practice

A team rebuilding the online registration of an adult education centre works in two-week Sprints that always start on a Wednesday. In the third Sprint, the goal is that participants can put themselves on a waiting list for fully booked courses. When management asks for an additional discount feature in the middle of the Sprint, the Product Owner adds it to the Product Backlog rather than changing the current Sprint. It is considered in the next Sprint Planning.

Frequently asked questions

Why does a Sprint last one month at most?

Longer periods increase the risk that goals become outdated and deviations are noticed late. Short Sprints ensure that the result and the approach are inspected regularly.

May a team change the Sprint length?

The Scrum Guide requires a fixed length so that a reliable rhythm develops. Teams therefore usually change the length only deliberately and rarely, for example after a Retrospective.

Source and context

Reference
Scrum Guide 2020, Abschnitt Der Sprint
Edition
Scrum Guide 2020

Differences from other editions

Scrum Guide 2017
Cancelling a Sprint was described in more detail: finished items were reviewed and usually accepted by the Product Owner, while unfinished ones were estimated again and returned to the Product Backlog. Every Sprint was regarded as a project whose horizon did not exceed one month.
Cite this entry
APA

Hain, D. (n.d.). Sprint. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/sprint/

Short form

Hain, D. (n.d.): Sprint. PMDecoder, entry on Scrum Guide 2020, Abschnitt Der Sprint. https://pmdecoder.com/en/glossary/sprint/ (retrieved 24 November 2026)

BibTeX
@misc{sprint,
  author  = {Hain, Dennis},
  title   = {Sprint},
  note    = {PMDecoder, Scrum Guide 2020, Abschnitt Der Sprint},
  url     = {https://pmdecoder.com/en/glossary/sprint/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/sprint/">
  <p>Fixed-length period of one month or less in which a Scrum Team works towards a Sprint Goal and which contains all other events</p>