Variance

Definition

A variance arises when actual results do not match the plan. The yardstick is not the current planning status at any given time but the approved baseline. Variances can concern schedule, cost, scope or quality and can be favourable or unfavourable. They are expressed in units such as days or euros, or as a percentage, and compared with variance thresholds to decide whether action is needed.

Equivalents in other frameworks

Concept Difference between plan and actual · one framework reviewed

Equivalents of Variance in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKVarianceequivalent—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Variance

Distinction

Variance analysis is the procedure for determining variances and investigating their causes. Cost variance and schedule variance are particular variances calculated with the earned value method. An issue is a problem that has occurred and may, but need not, cause a variance.

In practice

In the monthly report of a building project, the structural work shows a schedule variance of twelve working days and a cost variance of plus 40,000 euros. Site management attributes the delay to frost, which halted the concrete work; the work already performed, by contrast, cost somewhat less than budgeted. Because the schedule variance exceeds the agreed threshold of ten days, site management presents a plan for catching up; the cost variance requires no action.

Frequently asked questions

Is every variance a problem?

No. Small variances are normal, because no plan predicts reality exactly. What matters is whether they exceed agreed thresholds or show a trend.

Why measure against the baseline and not the current plan?

Because the current plan is adjusted continuously. If it were used as the yardstick, variances would vanish as soon as the plan had been updated, and the project's development could no longer be traced.

Source and context

Reference
ISO 21506:2024, 3.93
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Variance. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/variance/

Short form

Hain, D. (n.d.): Variance. PMDecoder, entry on ISO 21506:2024, 3.93. https://pmdecoder.com/en/glossary/variance/ (retrieved 24 November 2026)

BibTeX
@misc{variance,
  author  = {Hain, Dennis},
  title   = {Variance},
  note    = {PMDecoder, ISO 21506:2024, 3.93},
  url     = {https://pmdecoder.com/en/glossary/variance/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/variance/">
  <p>Gap between the approved baseline and what has actually been achieved, for example in schedule, cost or scope.</p>