Finish-to-finish relationship

abbr. FF

Definition

A finish-to-finish relationship links the completion of a predecessor to the completion of a successor. The successor may therefore not finish while the predecessor is still running. It is typical of accompanying tasks such as supervision, documentation or the provision of equipment, which are only to end once the actual work has been done.

Equivalents in other frameworks

Concept Finish after another activity finishes · three frameworks reviewed

Equivalents of Finish-to-finish relationship in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKFinish-to-finishequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Finish-to-finish relationship

Distinction

Whereas a finish-to-start relationship links a finish to a start, a finish-to-finish relationship ties two finishes together. The start-to-start relationship is its counterpart for the start. A hammock activity is often tied to the work it spans through both a start-to-start and a finish-to-finish relationship.

In practice

While a fire alarm system is being installed, a fire watch must be on site and may only withdraw once the system is in operation. The planner links the finish of commissioning to the finish of the fire watch with a finish-to-finish relationship. If installation takes three days longer, the scheduling software automatically extends the fire watch as well and makes the additional costs visible.

Frequently asked questions

How is the finish-to-finish relationship abbreviated?

In English as FF. In German, it is abbreviated as EF (Endfolge), and in German-language scheduling software often as EE (Ende-Ende).

What is a finish-to-finish relationship used for in practice?

Mainly for work that has to continue until another piece of work is complete, such as site supervision, hired equipment or accompanying documentation.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Finish-to-finish relationship. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/finish-to-finish-relationship/

Short form

Hain, D. (n.d.): Finish-to-finish relationship. PMDecoder. https://pmdecoder.com/en/glossary/finish-to-finish-relationship/ (retrieved 24 November 2026)

BibTeX
@misc{finishtofinishrelationship,
  author  = {Hain, Dennis},
  title   = {Finish-to-finish relationship},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/finish-to-finish-relationship/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/finish-to-finish-relationship/">
  <p>Logical relationship in which an activity can finish at the earliest once another activity has finished</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/finish-to-finish-relationship/">Finish-to-finish relationship</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.