Variance threshold

Definition

Variance thresholds sort out which variances the project absorbs itself and which call for a response. They are set before work starts, usually separately for schedule, cost and scope, and stated as absolute values or percentages, such as ten working days or five per cent of the budget. As long as a variance stays below the threshold, monitoring is enough. Once it is reached, it must be examined whether corrective action, a change to the plan or escalation to the next level up is required.

Equivalents in other frameworks

Concept Permitted margin for deviations · one framework reviewed

Equivalents of Variance threshold in other frameworks
FrameworkTerm thereRelationNote
PRINCE2Tolerance (PRINCE2)equivalent—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Variance threshold

Distinction

Risk tolerance relates to possible future events, the variance threshold to differences from the baseline that have already occurred. In PRINCE2, comparable limits are called tolerances and are firmly tied to escalation between management levels. A specification limit in quality control, by contrast, concerns characteristics of a product, not the course of the project.

In practice

A district council is having twelve schools refurbished as a programme. The rule for each project is: variances of up to five per cent of cost or two weeks of delay are handled by the project manager, up to ten per cent or four weeks by the programme manager, and anything beyond that by the district committee. When hazardous substances found at one school raise costs by eight per cent, the project manager presents two options to the programme manager; the committee does not need to be involved.

Frequently asked questions

How are sensible variance thresholds set?

According to the importance of the characteristic and the uncertainty of the planning. Tight thresholds suit undertakings that can be planned well, wider ones suit novel undertakings. Thresholds that are too tight lead to constant escalation, and thresholds that are too wide mean problems are noticed late.

Do thresholds only apply to individual values?

Not only. Many organizations also set trend thresholds, for example when a performance index deteriorates for three reporting periods in a row, even if the value itself is still within limits.

Source and context

Reference
ISO 21506:2024, 3.95
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Variance threshold. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/variance-threshold/

Short form

Hain, D. (n.d.): Variance threshold. PMDecoder, entry on ISO 21506:2024, 3.95. https://pmdecoder.com/en/glossary/variance-threshold/ (retrieved 24 November 2026)

BibTeX
@misc{variancethreshold,
  author  = {Hain, Dennis},
  title   = {Variance threshold},
  note    = {PMDecoder, ISO 21506:2024, 3.95},
  url     = {https://pmdecoder.com/en/glossary/variance-threshold/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/variance-threshold/">
  <p>Limit for variances, set in advance, that determines when the project manager or the sponsor has to step in.</p>