Variance threshold
Definition
Variance thresholds sort out which variances the project absorbs itself and which call for a response. They are set before work starts, usually separately for schedule, cost and scope, and stated as absolute values or percentages, such as ten working days or five per cent of the budget. As long as a variance stays below the threshold, monitoring is enough. Once it is reached, it must be examined whether corrective action, a change to the plan or escalation to the next level up is required.
Equivalents in other frameworks
Concept Permitted margin for deviations · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | Tolerance (PRINCE2) | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Variance threshold
- Topic area
- Monitoring and control
Distinction
Risk tolerance relates to possible future events, the variance threshold to differences from the baseline that have already occurred. In PRINCE2, comparable limits are called tolerances and are firmly tied to escalation between management levels. A specification limit in quality control, by contrast, concerns characteristics of a product, not the course of the project.
In practice
A district council is having twelve schools refurbished as a programme. The rule for each project is: variances of up to five per cent of cost or two weeks of delay are handled by the project manager, up to ten per cent or four weeks by the programme manager, and anything beyond that by the district committee. When hazardous substances found at one school raise costs by eight per cent, the project manager presents two options to the programme manager; the committee does not need to be involved.
Frequently asked questions
How are sensible variance thresholds set?
According to the importance of the characteristic and the uncertainty of the planning. Tight thresholds suit undertakings that can be planned well, wider ones suit novel undertakings. Thresholds that are too tight lead to constant escalation, and thresholds that are too wide mean problems are noticed late.
Do thresholds only apply to individual values?
Not only. Many organizations also set trend thresholds, for example when a performance index deteriorates for three reporting periods in a row, even if the value itself is still within limits.
Source and context
- Reference
- ISO 21506:2024, 3.95
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Variance threshold. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/variance-threshold/
Hain, D. (n.d.): Variance threshold. PMDecoder, entry on ISO 21506:2024, 3.95. https://pmdecoder.com/en/glossary/variance-threshold/ (retrieved 24 November 2026)
@misc{variancethreshold,
author = {Hain, Dennis},
title = {Variance threshold},
note = {PMDecoder, ISO 21506:2024, 3.95},
url = {https://pmdecoder.com/en/glossary/variance-threshold/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/variance-threshold/"> <p>Limit for variances, set in advance, that determines when the project manager or the sponsor has to step in.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/variance-threshold/">Variance threshold</a>, PMDecoder, ISO 21506:2024, 3.95</footer> </blockquote>
Found a mistake? Let us know, we check every report.