Residual risk
Definition
Hardly any response eliminates a risk completely. Residual risk describes the probability and impact that are left over after mitigation, transfer or other actions. It is reassessed, documented and either explicitly accepted by an authorized body or treated further. In safety-critical industries there are often binding requirements for assessing residual risks.
Equivalents in other frameworks
Concept Risk remaining after responses · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Residual risk | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Residual risk
- Topic area
- Risks and opportunities
Distinction
Inherent risk is the assessment before any response, residual risk the assessment afterwards. A secondary risk only arises as a result of a response, whereas residual risk is the remaining part of the original risk. Both belong in the risk register so that the overall picture stays complete.
In practice
A chemical company is planning a new filling line. The risk of a leak is reduced by drip trays, sensors and automatic shut-off valves. Simultaneous failure of all three systems is rated as very unlikely but serious. Plant management accepts this residual risk in writing and also has an emergency plan agreed with the local fire brigade. Whenever the plant is modified, the assessment is checked to see whether it still applies.
Frequently asked questions
Who accepts residual risks?
The body that has to answer for the consequences; for significant residual risks, the client or senior management.
Can residual risk be zero?
Rarely in practice. Only avoidance eliminates a risk completely, and even that can create new risks. More important than a value of zero is that the remaining risk is known and consciously borne.
Source and context
- Reference
- ISO 21506:2024, 3.72
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Residual risk. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/residual-risk/
Hain, D. (n.d.): Residual risk. PMDecoder, entry on ISO 21506:2024, 3.72. https://pmdecoder.com/en/glossary/residual-risk/ (retrieved 24 November 2026)
@misc{residualrisk,
author = {Hain, Dennis},
title = {Residual risk},
note = {PMDecoder, ISO 21506:2024, 3.72},
url = {https://pmdecoder.com/en/glossary/residual-risk/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/residual-risk/"> <p>Risk that remains once the agreed response actions have been carried out, assessed by likelihood and impact.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/residual-risk/">Residual risk</a>, PMDecoder, ISO 21506:2024, 3.72</footer> </blockquote>
Found a mistake? Let us know, we check every report.