Project Manager (PRINCE2)

Definition

The Project Manager in PRINCE2 runs the project day to day on behalf of the Project Board and within the limits it has set. The role is held by a single person. The Project Manager plans, allocates work packages, monitors progress, manages risks, issues and quality, and reports to the Project Board. The Project Manager is responsible for ensuring that the agreed products are delivered to the required quality, within time and cost, and with the benefits in mind. As long as tolerances are respected, the Project Manager acts independently; otherwise the matter is escalated. The role belongs to the managing level between direction and the teams.

Equivalents in other frameworks

Concept Person responsible for managing a project · five frameworks reviewed

Equivalents of Project Manager (PRINCE2) in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Project managerclosely relatedManages within the Project Board’s tolerances but owns neither the business case nor the decision to continue.
PMI / PMBOKProject managerclosely relatedManages within the Project Board’s tolerances but owns neither the business case nor the decision to continue.
PM²Project Managerclosely relatedin PM², explicitly belongs to the Provider Side and reports to the Solution Provider
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Project Manager (PRINCE2)

Distinction

The project manager in ISO 21506 and in PMI publications has a similar mandate. In PRINCE2, however, the role is clearly separated from the Project Board: the Project Manager does not decide whether the project continues and does not own the business case but prepares these decisions. The Project Manager should not also be a member of the Project Board.

In practice

A retail company is opening twelve new branches. The project manager plans the stages, allocates work packages to shopfitting, IT and human resources and produces a progress report every two weeks. When two sites cannot be finished on time because building permits are missing, she presents options to the Project Board instead of changing the order of openings on her own authority.

Frequently asked questions

Can the Project Manager also be Team Manager?

Yes. On small projects the Project Manager often leads the teams directly, so no separate team management role is filled.

Who appoints the Project Manager?

Usually the Executive, in agreement with the commissioning organization. This happens during start-up, before initiation begins.

Source and context

Reference
PRINCE2 7, Praktik Organisation
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Project Manager (PRINCE2). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-manager-prince2/

Short form

Hain, D. (n.d.): Project Manager (PRINCE2). PMDecoder, entry on PRINCE2 7, Praktik Organisation. https://pmdecoder.com/en/glossary/project-manager-prince2/ (retrieved 24 November 2026)

BibTeX
@misc{projectmanagerprince2,
  author  = {Hain, Dennis},
  title   = {Project Manager (PRINCE2)},
  note    = {PMDecoder, PRINCE2 7, Praktik Organisation},
  url     = {https://pmdecoder.com/en/glossary/project-manager-prince2/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/project-manager-prince2/">
  <p>PRINCE2 role that runs the project day to day on behalf of the Project Board and has the products delivered within tolerances.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-manager-prince2/">Project Manager (PRINCE2)</a>, PMDecoder, PRINCE2 7, Praktik Organisation</footer>
</blockquote>

Found a mistake? Let us know, we check every report.