Closing Phase
Definition
In the Closing Phase, the last phase of the PM² life cycle, the finished results formally pass into the responsibility of the Project Owner. The phase begins with the Project-End Review Meeting, in which the team and other participants look back on performance, collaboration and experience. The Project Manager then summarizes results, good practices, difficulties and recommendations in the Project-End Report. Administrative closure includes archiving all project documents and releasing the resources. The phase ends with the final approval by the Project Owner.
Equivalents in other frameworks
Concept Closing stage of a project · five frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PRINCE2 | Closing a project | closely related | Process within the final stage rather than a stage of its own; also used for premature closure. |
| Six Sigma | Control phase | closely related | Closes the project, but focuses on securing the improvement for the long term and handing it over to the process owner. |
| general | Project closure | closely related | fixed phase after the Ready for Closing phase gate, with the Project-End Report |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Closing Phase
- Topic area
- Closing
Distinction
The general term project closure describes the end of a project independently of any method. In PM², the Closing Phase also applies when a project is not approved after initiation: it then goes straight into closing so that the experience gained is preserved.
In practice
After the launch of a new e-procurement portal, the Project Manager invites the participants to the closing meeting. The group also assesses the performance of the external service provider and records that involving the contracting units early on saved time. The Project-End Report recommends extending the portal with electronic requests for missing documents as a follow-up project.
Frequently asked questions
What happens if a project ends early?
The Closing Phase is carried out in that case too, so that documents are archived, resources are released and lessons are recorded for future projects.
Who decides on the end of the Closing Phase?
The Project Owner, by giving the final approval that marks the administrative closure.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitte 3.2.4 und 8
- Edition
- PM² Guide 3.1
Cite this entry
Closing Phase. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/closing-phase-pm2/
Closing Phase (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitte 3.2.4 und 8. https://pmdecoder.com/en/glossary/closing-phase-pm2/ (retrieved 24 November 2026)
@misc{closingphasepm2,
title = {Closing Phase},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitte 3.2.4 und 8},
url = {https://pmdecoder.com/en/glossary/closing-phase-pm2/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/closing-phase-pm2/"> <p>Last PM² phase, in which the results are handed over, experience is evaluated and the project is closed administratively</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/closing-phase-pm2/">Closing Phase</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitte 3.2.4 und 8</footer> </blockquote>
Found a mistake? Let us know, we check every report.