Finish-to-start relationship
abbr. FS
Definition
A finish-to-start relationship links the finish of a predecessor to the start of a successor. It is the most natural form of dependency: only when one piece of work is complete can the next build on it. A time interval can express that there is a waiting period in between, for example for curing, or that the two may overlap by a certain amount of time.
Equivalents in other frameworks
Concept Start after the predecessor finishes · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Finish-to-start | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Logical relationship
- this term
- Finish-to-start relationship
- Topic area
- Network planning
Distinction
The finish-to-start relationship is one of four logical relationships. Start-to-start links two starts, finish-to-finish two finishes, and start-to-finish ties the start of the predecessor to the finish of the successor. In scheduling tools, finish-to-start is usually the default.
In practice
In a software project, acceptance testing can only begin once installation on the test system is complete. The planner links the two activities with a finish-to-start relationship. Because the test team needs another day after installation to load test data, she also enters a time interval of one day. If the installation is delayed, the software automatically moves the start of testing.
Frequently asked questions
How is the finish-to-start relationship abbreviated?
In English-language scheduling software as FS. In German, it is abbreviated as NF (Normalfolge) in network planning and often as EA (Ende-Anfang) in scheduling software.
Can a finish-to-start relationship allow an overlap?
Yes, through a negative time interval. The successor may then start before the predecessor is fully complete.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Finish-to-start relationship. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/finish-to-start-relationship/
Hain, D. (n.d.): Finish-to-start relationship. PMDecoder. https://pmdecoder.com/en/glossary/finish-to-start-relationship/ (retrieved 24 November 2026)
@misc{finishtostartrelationship,
author = {Hain, Dennis},
title = {Finish-to-start relationship},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/finish-to-start-relationship/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/finish-to-start-relationship/"> <p>Logical relationship in which an activity can only start once its predecessor has finished</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/finish-to-start-relationship/">Finish-to-start relationship</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.