Work Package

Definition

In PRINCE2, a work package is a set of information with which the project manager assigns responsibility for delivering one or more products to a team manager. It contains the product descriptions of the products to be delivered, agreed dates and effort, tolerances, constraints, techniques to be used, how progress is reported to the project manager and the procedure for handing over the finished products. The project manager authorizes the work package as part of stage control, and the team manager accepts it after both have agreed on content and feasibility. This links the teams’ work to project control without the project manager having to plan every activity.

Equivalents in other frameworks

Concept Smallest planning unit of the project structure · two frameworks reviewed

Equivalents of Work Package in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Work packageclosely relatedIn PRINCE2 above all an agreement between project manager and team manager on delivery, tolerances and reporting; can cover several products.
PMI / PMBOKWork packageclosely relatedIn PRINCE2 above all an agreement between project manager and team manager on delivery, tolerances and reporting; can cover several products.

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Work Package

Distinction

In the work breakdown structure under ISO 21506 and in PMI, the work package is the lowest unit of the scope breakdown. The PRINCE2 work package, by contrast, is above all an agreement on delivery and control and can cover several products. It contains more than a work package description, namely tolerances and reporting arrangements as well.

In practice

In a project to modernize a production line, the project manager hands the electrical workshop’s team manager a work package: rebuild the control cabinet and connect the controls. Attached are the product descriptions, a time window during the plant shutdown, a tolerance of two days and the requirement to report status briefly each day. The team manager reviews the documents, asks for an additional electrician and then accepts the work package.

Frequently asked questions

Can a work package go to an external supplier?

Yes. It should then be consistent with the contractual arrangements. In that case the team manager is often a person on the supplier’s side.

Does a work package have to be in writing?

The form depends on the project. In small projects a verbal agreement may be enough, as long as content, tolerances and handover are clear and recorded.

Source and context

Reference
PRINCE2 7, Managementprodukte
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Work Package. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/work-package-prince2/

Short form

Hain, D. (n.d.): Work Package. PMDecoder, entry on PRINCE2 7, Managementprodukte. https://pmdecoder.com/en/glossary/work-package-prince2/ (retrieved 24 November 2026)

BibTeX
@misc{workpackageprince2,
  author  = {Hain, Dennis},
  title   = {Work Package},
  note    = {PMDecoder, PRINCE2 7, Managementprodukte},
  url     = {https://pmdecoder.com/en/glossary/work-package-prince2/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/work-package-prince2/">
  <p>In PRINCE2, the agreed transfer of responsibility for delivering specific products from the project manager to a team manager.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/work-package-prince2/">Work Package</a>, PMDecoder, PRINCE2 7, Managementprodukte</footer>
</blockquote>

Found a mistake? Let us know, we check every report.