Variance at completion
Definition
In PMI usage, variance at completion (VAC) is a projection of the budget variance expected at the end of the project, calculated as BAC minus EAC, the approved budget less the current total forecast. A negative value means the project is expected to cost more than budgeted, a positive value that it will need less. VAC is therefore not a measured but a forecast quantity; its quality depends on how well the estimate at completion is founded. It is usually shown in the regular earned value reports.
Equivalents in other frameworks
Concept Expected budget variance at completion · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Variance at completion | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Variance at completion
- Topic area
- Monitoring and control
Distinction
The term is equivalent to the ISO 21506 term variance at completion. Cost variance measures the cost variance that has already occurred at the status date, VAC the one expected at the end. The estimate at completion states the expected total cost, VAC its distance from the budget.
In practice
A project to rebuild a data centre has a budget at completion of 2.4 million euros. After analysing the cost efficiency so far and re-estimating the remaining work, the estimate at completion is 2.6 million euros. The VAC is minus 200,000 euros. The project manager presents two options to the sponsor: additional funds from the management reserve or dropping the renewal of the cooling in an auxiliary room.
Frequently asked questions
How can a negative VAC be reduced?
Through more efficient work, cheaper procurement, an adjustment of scope or the use of reserves. Which option is possible is usually not decided by the project manager alone.
When does VAC become meaningful?
Once a substantial part of the work has been performed and the indicators are stable. In early phases the estimate at completion is still uncertain, and so is the VAC.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Variance at completion. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/variance-at-completion-pmi/
Variance at completion (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/variance-at-completion-pmi/ (retrieved 24 November 2026)
@misc{varianceatcompletionpmi,
title = {Variance at completion},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/variance-at-completion-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/variance-at-completion-pmi/"> <p>Expected budget variance at project end: budget at completion minus estimate at completion.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/variance-at-completion-pmi/">Variance at completion</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.