Precedence diagramming method

Definition

The precedence diagramming method, PDM for short, is the technique used to build a schedule model as a network: each activity is represented as a node, usually a box, and the logical relationships between activities are drawn as arrows. PDM allows all four relationship types, finish-to-start, finish-to-finish, start-to-start and start-to-finish, each with a possible lag or lead. The representation is also known as activity-on-node. It underlies almost all current scheduling tools and is the usual input for calculation with the critical path method.

Equivalents in other frameworks

Concept Network diagram with activities on nodes · three frameworks reviewed

Equivalents of Precedence diagramming method in other frameworks
FrameworkTerm thereRelationNote
generalActivity-on-node networkclosely relatednames the diagramming method, the activity-on-node network diagram its result
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Precedence diagramming method

Distinction

The precedence diagramming method is close to the German Vorgangsknotennetzplan, but strictly speaking it refers to the technique, while the Vorgangsknotennetzplan is the result. In an activity-on-arrow network (Vorgangspfeilnetzplan), activities lie on the arrows, and dummy activities are often needed to represent dependencies correctly. PMI calls the finished diagram a project schedule network diagram.

In practice

A municipal utility is planning to replace a water main. The project manager first lays out the activities on cards on a pinboard and links them with arrows, choosing a start-to-start relationship with a lag for trenching and pipe laying, because pipe laying can follow section by section. She then transfers the resulting network into the scheduling tool.

Frequently asked questions

Why has the precedence diagramming method prevailed over arrow networks?

It needs no dummy activities, allows all four relationship types and is easier to read and change. In addition, practically all common scheduling tools work on this principle.

Does the network need to be drawn if a tool does the calculation?

Not necessarily, but a graphical view helps to spot missing or implausible dependencies. Many teams sketch the network together before entering it into the tool.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Precedence diagramming method. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/precedence-diagramming-method/

Short form

Precedence diagramming method (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/precedence-diagramming-method/ (retrieved 24 November 2026)

BibTeX
@misc{precedencediagrammingmethod,
  title   = {Precedence diagramming method},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/precedence-diagramming-method/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/precedence-diagramming-method/">
  <p>Scheduling technique that draws activities as boxes (nodes) and connects them with arrows for their logical dependencies.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/precedence-diagramming-method/">Precedence diagramming method</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.