Risk analysis
Definition
In PMI terms, risk analysis is the work that lies between identifying risks and dealing with them. Identified risks are examined to determine how likely they are to occur, how strongly they would affect which objectives, and which other characteristics matter, such as urgency, proximity of possible occurrence or links to other risks. PMI distinguishes two forms: qualitative analysis, which prioritizes risks by means of ratings, and quantitative analysis, which numerically estimates the combined effect of risks on the overall result. The outcome forms the basis for choosing risk responses.
Equivalents in other frameworks
Concept Examination of identified risks · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| general | Risk analysis | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- Broader term
- Risk management
- this term
- Risk analysis
- Narrower terms
- Qualitative risk analysisQuantitative risk analysis
- Topic area
- Risks and opportunities
Distinction
The term corresponds to the cross-framework concept of risk analysis. It is the umbrella term for qualitative risk analysis and quantitative risk analysis. It differs from risk identification in that the latter finds and describes risks; analysis evaluates them. Selecting actions already belongs to risk response.
In practice
After a workshop, a construction project has 40 risks on record. The team rates each one using a probability and impact matrix. For the twelve highest-rated risks it also runs a simulation of their schedule impact to see how likely the planned handover date still is.
Frequently asked questions
Does every project need quantitative analysis?
No. Qualitative analysis is appropriate almost always. Quantitative analysis is mainly worthwhile for large, complex or strategically important projects and requires reliable data.
How often is risk analysis performed?
Repeatedly throughout the life of the project. New risks emerge, and the assessment of known risks changes as more information becomes available.
Source and context
- Reference
- PMI Lexicon of Project Management Terms 4.0 (2024)
- Edition
- PMBOK Guide – Eighth Edition
Cite this entry
Risk analysis. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/risk-analysis-pmi/
Risk analysis (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/risk-analysis-pmi/ (retrieved 24 November 2026)
@misc{riskanalysispmi,
title = {Risk analysis},
note = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
url = {https://pmdecoder.com/en/glossary/risk-analysis-pmi/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/risk-analysis-pmi/"> <p>Examination of identified risks by probability, impact and other characteristics in order to prioritize them and prepare responses.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/risk-analysis-pmi/">Risk analysis</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer> </blockquote>
Found a mistake? Let us know, we check every report.