Resource planning

also: Capacity planning

Definition

Resource planning derives the demand for staff, equipment and materials from activities, effort and dates. It defines which skills are needed, how many people are deployed at which times and which equipment or rooms have to be reserved. The demand is then compared with availability, and bottlenecks are resolved by rescheduling, buying in capacity or setting priorities.

Equivalents in other frameworks

Concept Determining resource needs and deployment · one framework reviewed

Equivalents of Resource planning in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKResource management planpartially overlappingdenotes the plan containing the rules for acquiring, deploying and releasing resources

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Other terms

Other words for the same thing in English usage. Not to be confused with the equivalents above, which translate between frameworks.

Capacity planning
synonym
Resource management
related, not equivalent

Classification

this term
Resource planning

Distinction

Resource planning determines demand and assignment; resource levelling then removes overloads. Staffing planning is the part of it that concerns people only. In multi-project management, resource planning is carried out across projects, because the same people work on several initiatives.

In practice

An IT department with forty employees supports twelve projects at the same time. In the past, each project manager sent their demand to the team leads by e-mail; today everyone enters it by role and calendar week in a shared overview. The first comparison shows that the two database specialists are booked at 180 per cent in the autumn. The head of department postpones one project by six weeks and engages an external service provider for another.

Frequently asked questions

How far ahead should resources be planned?

Roughly for the entire project duration, and bindingly for the next weeks to months. For scarce specialists and hired equipment, a longer lead time pays off.

What is a resource request?

The formal request for staff or equipment addressed to the responsible unit, such as line management or purchasing. It makes demands binding and traceable.

Source and context

Cite this entry
APA

Hain, D. (n.d.). Resource planning. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/resource-planning/

Short form

Hain, D. (n.d.): Resource planning. PMDecoder. https://pmdecoder.com/en/glossary/resource-planning/ (retrieved 24 November 2026)

BibTeX
@misc{resourceplanning,
  author  = {Hain, Dennis},
  title   = {Resource planning},
  note    = {PMDecoder},
  url     = {https://pmdecoder.com/en/glossary/resource-planning/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/resource-planning/">
  <p>Determining which resources a project needs, when and to what extent, and matching this demand against the available capacity</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/resource-planning/">Resource planning</a>, PMDecoder</footer>
</blockquote>

Found a mistake? Let us know, we check every report.