Lead

Definition

A lead allows two linked activities to overlap. With a finish-to-start relationship and a lead of five days, the successor starts five days before its predecessor ends. In the network schedule it is entered as a negative time offset. It reflects the fact that follow-on work can begin with interim results without abandoning the dependency altogether.

Equivalents in other frameworks

Concept Brought-forward start relative to the predecessor · three frameworks reviewed

Equivalents of Lead in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKLeadequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Lead

Distinction

Lag is the counterpart and enforces a waiting time between two activities. In general usage, lead time also refers to the time between ordering and availability, such as the delivery time of a machine; in the schedule, such a period is usually shown as a separate activity. A lead is one of the means used in fast tracking.

In practice

An editorial team is producing an annual report. Layout can begin once two thirds of the texts are ready, because the basic design does not depend on the last chapters. The project manager links writing and layout with a finish-to-start relationship and a ten-day lead. As a result, the report is published two weeks earlier. When one chapter is heavily rewritten, a few hours of layout rework arise, as expected.

Frequently asked questions

How is a lead entered in scheduling software?

Usually as a negative offset on the link, for example minus five days, sometimes also as a percentage of the predecessor's duration.

What is the risk of a lead?

The successor works with unfinished results. If these still change, rework follows.

Source and context

Reference
ISO 21506:2024, 3.33
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Lead. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/lead/

Short form

Hain, D. (n.d.): Lead. PMDecoder, entry on ISO 21506:2024, 3.33. https://pmdecoder.com/en/glossary/lead/ (retrieved 24 November 2026)

BibTeX
@misc{lead,
  author  = {Hain, Dennis},
  title   = {Lead},
  note    = {PMDecoder, ISO 21506:2024, 3.33},
  url     = {https://pmdecoder.com/en/glossary/lead/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/lead/">
  <p>Negative time offset on a dependency that allows a successor to start or finish earlier than the link would otherwise permit.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/lead/">Lead</a>, PMDecoder, ISO 21506:2024, 3.33</footer>
</blockquote>

Found a mistake? Let us know, we check every report.