Planned value

Definition

In PMI usage, planned value (PV) is the approved budget allocated to the work that the schedule foresees. At any status date, cumulative planned value states how much work, expressed in budget units, should have been completed by then. Summed over the whole duration, it equals the budget at completion. Planned value is derived from the performance measurement baseline and is one of the three basic quantities of earned value analysis, together with earned value and actual cost. It does not include management reserve.

Equivalents in other frameworks

Concept Budgeted value of planned work · three frameworks reviewed

Equivalents of Planned value in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Planned valueequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Planned value

Distinction

The term is equivalent to the ISO 21506 term planned value. Planned value says nothing about what has actually been achieved; that is what earned value expresses. Nor should it be confused with planned spending in the sense of a payment plan, because it reflects the value of work rather than the date on which invoices are paid. The earlier term was budgeted cost of work scheduled (BCWS).

In practice

A project to modernize a production line has a budget of 1.5 million euros and a duration of twelve months. According to the schedule, dismantling, foundation work and delivery of the first machines are to be completed by the end of May; their budgets add up to 520,000 euros. That is the cumulative planned value at this status date. If earned value at the end of May is 460,000 euros, the project is behind schedule.

Frequently asked questions

How is the planned value curve created?

The budgets of the work packages or control accounts are spread over time according to the schedule and accumulated. The result is usually an S-shaped curve, because work intensity is highest in the middle of a project.

Does planned value change during the project?

Only when approved changes are made to the baseline, for example additional scope. Delays alone do not change planned value; otherwise the schedule variance would disappear.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Planned value. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/planned-value-pmi/

Short form

Planned value (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/planned-value-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{plannedvaluepmi,
  title   = {Planned value},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/planned-value-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/planned-value-pmi/">
  <p>Approved budget for the work that, according to the schedule, should be finished by a given status date.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/planned-value-pmi/">Planned value</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.