Benefits Management Approach

Definition

The benefits management approach describes how the expected benefits of a PRINCE2 project are to be demonstrated. It records which benefits are measured, with which measures and baselines, who is responsible for measuring and when this takes place. Because many benefits only arise once the outputs are used in everyday work, the planned reviews usually extend beyond the end of the project. The approach is created during initiation, updated at stage boundaries and handed over at closure to the organization responsible for later reviews. It complements the business case, which justifies the benefits, with the question of how they will be demonstrated.

Equivalents in other frameworks

Concept Planning and securing benefits of initiatives · two frameworks reviewed

Equivalents of Benefits Management Approach in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKBenefits management planpartially overlappingdenotes the plan that records benefits, their measurement and responsibilities
generalBenefits managementpartially overlappingManagement product defining how benefits are measured and reviewed, not the whole activity.

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Benefits Management Approach

Distinction

The business case answers why a project is worthwhile, the benefits management approach how this will later be shown. In content it largely corresponds to the PMI benefits management plan; general benefits management, by contrast, refers to the whole activity rather than a single document.

In practice

A logistics company introduces route-planning software and expects the kilometres driven to fall by eight per cent. The benefits management approach specifies using the average of the three months before introduction as the baseline, measuring again six and twelve months afterwards and entrusting the fleet manager with the evaluation. The second measurement takes place long after the project has closed.

Frequently asked questions

Who is responsible for benefits reviews after the project ends?

The commissioning organization, because the project team has been disbanded by then. The approach should therefore name who takes over the measurements and who receives the results.

Are negative effects also considered?

Yes. Besides benefits, PRINCE2 recognizes negative consequences that someone perceives as disadvantageous. They are described and measured in the same way so that the overall picture is accurate.

Source and context

Reference
PRINCE2 7, Praktik Business Case
Edition
PRINCE2 7
Cite this entry
APA

Hain, D. (n.d.). Benefits Management Approach. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/benefits-management-approach/

Short form

Hain, D. (n.d.): Benefits Management Approach. PMDecoder, entry on PRINCE2 7, Praktik Business Case. https://pmdecoder.com/en/glossary/benefits-management-approach/ (retrieved 24 November 2026)

BibTeX
@misc{benefitsmanagementapproach,
  author  = {Hain, Dennis},
  title   = {Benefits Management Approach},
  note    = {PMDecoder, PRINCE2 7, Praktik Business Case},
  url     = {https://pmdecoder.com/en/glossary/benefits-management-approach/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/benefits-management-approach/">
  <p>PRINCE2 management product defining how and when a project’s benefits are measured and reviewed, including after the project ends.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/benefits-management-approach/">Benefits Management Approach</a>, PMDecoder, PRINCE2 7, Praktik Business Case</footer>
</blockquote>

Found a mistake? Let us know, we check every report.