Schedule performance index
abbr. SPI
Definition
The schedule performance index shows how fast a project is progressing compared with the plan, calculated as earned value divided by planned value. A value of 0.9 means that only 90 per cent of the planned work had been done by the cut-off date. The index is useful for comparing projects and for identifying trends over several reporting periods. For a rough schedule forecast, the planned duration is divided by the index.
Equivalents in other frameworks
Concept Schedule efficiency of work performed · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Schedule performance index | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Schedule performance index
- Topic area
- Monitoring and control
Distinction
The cost performance index measures cost efficiency, the schedule performance index progress. Only together do they give a full picture: a project can be on time but expensive, or cheap but slow. Because earned value always equals planned value at the end, the schedule performance index rises towards one as the project nears completion, even if it finishes late.
In practice
In a project to digitize building records, the schedule performance index is 0.85 after two months. At the same pace, the planned duration of twelve months would stretch to a little over fourteen. When the index falls further to 0.80 over the next two months, the client approves additional scanning workstations. A month later the value rises again to 0.93.
Frequently asked questions
How is the schedule performance index calculated?
As earned value divided by planned value, both cumulative up to the cut-off date.
Does the index replace schedule planning?
No. It shows overall progress but not whether critical activities are affected. The network schedule with its critical path is still needed for that.
Source and context
- Reference
- ISO 21506:2024, 3.84
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Schedule performance index. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/schedule-performance-index/
Hain, D. (n.d.): Schedule performance index. PMDecoder, entry on ISO 21506:2024, 3.84. https://pmdecoder.com/en/glossary/schedule-performance-index/ (retrieved 24 November 2026)
@misc{scheduleperformanceindex,
author = {Hain, Dennis},
title = {Schedule performance index},
note = {PMDecoder, ISO 21506:2024, 3.84},
url = {https://pmdecoder.com/en/glossary/schedule-performance-index/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/schedule-performance-index/"> <p>Ratio of earned value to planned value; values below one indicate that the project is behind plan.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/schedule-performance-index/">Schedule performance index</a>, PMDecoder, ISO 21506:2024, 3.84</footer> </blockquote>
Found a mistake? Let us know, we check every report.