Burn-down chart
also: Burn-down diagram
Definition
A burn-down chart shows how much work remains to be done in a given period. The horizontal axis shows time, for example the days of an iteration, and the vertical axis the remaining work, measured in tasks, hours or story points. A straight line from the starting value to zero at the end date serves as a guide. If the actual curve lies above it, the team is behind; if it lies below, the team is progressing faster than planned. Burn-down charts are commonly used for a single iteration and for a release spanning several iterations.
Equivalents in other frameworks
Concept Chart of remaining work over time · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Burndown chart | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Burn-down chart
- Topic area
- Approaches and agility
Distinction
A burn-up chart instead shows completed work and total scope as two lines. This makes it visible whether a team is progressing slowly or whether the scope has grown; in a burn-down chart, the two causes cannot be distinguished. The S-curve of traditional planning also tracks progress over time, but as cumulative values. The Scrum Guide mentions burn-down charts only as one of several ways of forecasting progress and does not prescribe them.
In practice
In a Sprint of ten working days, a team starts with 40 story points. After five days, the burn-down chart still shows 32 open points instead of the expected 20. In the Daily Scrum it becomes clear that the interface to a legacy system requires more work than estimated. The Product Owner and the Developers agree to remove a less important item from the Sprint so that the Sprint Goal remains achievable.
Frequently asked questions
What does a flat line in the burn-down chart mean?
That no work has been reported as done for several days. This may be due to impediments, but also to items only being fully completed late.
Is a burn-down chart mandatory in Scrum?
No. The Scrum Guide mentions it only as a possible aid. What matters more is that the Developers regularly inspect their progress towards the Sprint Goal.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Burn-down chart. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/burn-down-chart/
Hain, D. (n.d.): Burn-down chart. PMDecoder. https://pmdecoder.com/en/glossary/burn-down-chart/ (retrieved 24 November 2026)
@misc{burndownchart,
author = {Hain, Dennis},
title = {Burn-down chart},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/burn-down-chart/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/burn-down-chart/"> <p>Chart showing the remaining work over time, with an ideal line indicating whether a team is likely to reach its goal</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/burn-down-chart/">Burn-down chart</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.