Control plan

Definition

A control plan describes how a process is kept in the state achieved after an improvement. It is usually kept as a table and, for each monitored measure, states the characteristic, the measurement method, sample size and frequency, limits or target values, the person responsible and the intended reaction to deviations. Both output measures and the most important influencing factors identified as decisive in the analysis are monitored. The plan is created in the Control phase of a DMAIC project and is handed over to the process owner. German translations vary.

Equivalents in other frameworks

Concept Setting quality objectives and checks · three frameworks reviewed

Equivalents of Control plan in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKQuality management planpartially overlappingdenotes the document in which the result of quality planning is recorded
PRINCE2Quality Management Approachpartially overlappingDefines standards, procedures and responsibilities; the quality criteria of individual products are in the product descriptions.
generalQuality planningpartially overlappingSets monitoring and reactions for a running process after the project, not quality assurance of the project results.

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Control plan
Topic area
Quality

Distinction

Quality planning sets out for a project how the quality of its results will be assured. A control plan, by contrast, applies to a running process and its operation after the project. A control chart is a tool that the control plan may call for; the plan additionally sets responsibilities and reactions.

In practice

After a project on billing errors, an energy supplier includes three measures in the control plan: the share of incorrect bills, evaluated monthly, the time taken to transmit meter readings, measured daily, and the number of blocked bills. If transmission time exceeds two days, the system notifies the team leader, who clarifies the cause within a week.

Frequently asked questions

Who is responsible for the control plan?

The project team drafts it; after handover the process owner is responsible for applying it. The process owner should therefore help to shape it.

When is a control plan changed?

When the process changes, a measure loses its significance or reactions prove ineffective. It is a living document, not a one-off project report.

Source and context

Reference
ISO 13053-2:2011
Edition
ISO 13053-2:2011 (tools and techniques)
Cite this entry
APA

Control plan. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/control-plan/

Short form

Control plan (n.d.). PMDecoder, entry on ISO 13053-2:2011. https://pmdecoder.com/en/glossary/control-plan/ (retrieved 24 November 2026)

BibTeX
@misc{controlplan,
  title   = {Control plan},
  note    = {PMDecoder, ISO 13053-2:2011},
  url     = {https://pmdecoder.com/en/glossary/control-plan/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/control-plan/">
  <p>Specification of which characteristics of an improved process are monitored, how, how often and by whom, and what happens when they deviate.</p>