Variance at completion
abbr. VAC
Definition
Variance at completion looks ahead to the end of the project. In earned value management it is calculated by subtracting the estimate at completion from the budget at completion. A negative value means that the work is likely to cost more than planned, a positive value that some budget should be left over. Because it is based on a forecast, it changes with every new estimate and is only as robust as the assumptions behind it.
Equivalents in other frameworks
Concept Expected budget variance at completion · one framework reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Variance at completion | equivalent | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Variance at completion
- Topic area
- Monitoring and control
Distinction
Cost variance measures what has already happened up to the cut-off date, variance at completion what is expected by the end. A project can be within budget today and still have a clearly negative variance at completion if its most expensive risks still lie ahead.
In practice
A museum plans an exhibition with a budget at completion of 900,000 euros. When the exhibition design contract is awarded, the bids come in above the cost estimate, and the new estimate at completion is 975,000 euros. The project manager presents the variance at completion of minus 75,000 euros to the museum's directors, together with two options: dropping a media room or releasing funds from the management reserve.
Frequently asked questions
At what variance at completion should action be taken?
When it exceeds the agreed variance threshold. Many organizations set percentages of the budget for this, above which the client or the steering committee has to be informed.
Is a positive variance at completion a success?
Not necessarily. It can point to efficiency, but also to budgets that were set too generously or to work that has not yet been fully captured.
Source and context
- Reference
- ISO 21506:2024, 3.94
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Variance at completion. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/variance-at-completion/
Hain, D. (n.d.): Variance at completion. PMDecoder, entry on ISO 21506:2024, 3.94. https://pmdecoder.com/en/glossary/variance-at-completion/ (retrieved 24 November 2026)
@misc{varianceatcompletion,
author = {Hain, Dennis},
title = {Variance at completion},
note = {PMDecoder, ISO 21506:2024, 3.94},
url = {https://pmdecoder.com/en/glossary/variance-at-completion/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/variance-at-completion/"> <p>Budget at completion minus estimate at completion; shows how far the total cost is expected to depart from the plan.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/variance-at-completion/">Variance at completion</a>, PMDecoder, ISO 21506:2024, 3.94</footer> </blockquote>
Found a mistake? Let us know, we check every report.