Work breakdown structure

Definition

In PMI usage, the work breakdown structure, or WBS, is the hierarchical breakdown of the entire scope of work that the project team has to carry out in order to reach the project objectives and produce the required deliverables. Each lower level describes the work in more detail; the lowest level consists of work packages. The WBS is deliverable-oriented and follows the principle that all components together cover exactly the entire scope, no more and no less. It serves as the basis for estimating, scheduling, cost planning, assigning responsibilities and measuring progress. PMI has published a separate practice standard on it.

Equivalents in other frameworks

Concept Hierarchical decomposition of project scope · four frameworks reviewed

Equivalents of Work breakdown structure in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Work breakdown structureequivalent—
ISO 21506Product breakdown structurepartially overlappingbreaks down the result into sub-products instead of the work into work packages
PRINCE2Product Breakdown Structurepartially overlappingBreakdown into products rather than work; corresponds to the product breakdown structure under ISO 21506.
ScrumProduct Backlogpartially overlappingalso decomposes the scope, but ordered by value rather than hierarchically

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Work breakdown structure

Distinction

The work breakdown structure as defined in ISO 21506 is the cross-framework term for the same thing; this entry gives the PMI view. The WBS breaks down work and results, not the sequence in time, which is shown by the project schedule. A product backlog in Scrum fulfils part of the same function but is a prioritized list rather than a complete hierarchy.

In practice

A municipal utility is introducing a customer portal. At the first level, the WBS divides the project into portal, interfaces, data migration, roll-out and project management. Under roll-out come training, a communications campaign and pilot operation. During the review it becomes apparent that accessibility testing appears nowhere; it is added as a separate work package before the schedule and costs are planned.

Frequently asked questions

Should a WBS be structured by phases or by deliverables?

Both are possible. PMI emphasizes a deliverable orientation because it then becomes clear which result each component produces. Structuring by phases at the first level can make sense if the project runs in distinct phases.

Does project management work belong in the WBS?

Yes. Planning, control, reporting and closure also cause effort and cost. If they are missing from the WBS, estimates and budget are incomplete.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Work breakdown structure. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/

Short form

Work breakdown structure (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/ (retrieved 24 November 2026)

BibTeX
@misc{workbreakdownstructurepmi,
  title   = {Work breakdown structure},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/">
  <p>Deliverable-oriented breakdown of the entire project scope into levels down to work packages that together cover exactly this scope.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/work-breakdown-structure-pmi/">Work breakdown structure</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.