Backward pass
also: Backward pass calculation
Definition
The backward pass starts at the end activity with the target date, usually the result of the forward pass or a specified end date. From there, each activity is given a late finish, derived from the latest possible start of its successors, and a late start, obtained by subtracting the duration. If an activity has several successors, the one that has to start first is decisive.
Equivalents in other frameworks
Concept Calculation of latest dates · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Backward pass | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Backward pass
- Topic area
- Network planning
Distinction
The forward pass provides the earliest possible dates, the backward pass the latest permissible ones. The difference between the two is an activity's total float. If the specified end date lies before the result of the forward pass, negative float results, and the project cannot be finished on time without countermeasures.
In practice
In the example with A (four days), B (six days), C (three days) and D (two days), the backward pass begins on day 12. D must start on day 10 at the latest, so B and C must be finished by day 10. B must therefore start on day 4 at the latest, C not until day 7. A must finish on day 4 because B must start then. C thus has three days of room to manoeuvre, while A, B and D have none.
Frequently asked questions
Why is the successor that has to start first decisive?
Because an activity must be finished before the first of its successors starts at its latest. Any later finish would delay this successor.
What is the backward pass used for in practice?
It shows by when work must be done at the latest and thus makes room to manoeuvre and critical activities visible.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Backward pass. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/backward-pass/
Hain, D. (n.d.): Backward pass. PMDecoder. https://pmdecoder.com/en/glossary/backward-pass/ (retrieved 24 November 2026)
@misc{backwardpass,
author = {Hain, Dennis},
title = {Backward pass},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/backward-pass/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/backward-pass/"> <p>Calculation of the latest permissible finish and start dates of all activities, working from the project end against the dependencies</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/backward-pass/">Backward pass</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.