Project Owner
abbr. PO
Definition
In PM², the Project Owner (PO) acts as the project's client. The role determines which business objectives the project pursues and ensures that the results fit the organization's priorities. The Project Owner is accountable for overall success, bears the business risks, provides the agreed resources, chairs the Project Steering Committee and approves the key artefacts, from the Business Case to the Transition Plan. After the project, responsibility for the product or service passes to the Project Owner.
Equivalents in other frameworks
Concept Senior sponsoring role in a project · six frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Sponsor | closely related | in PM², also sets the business objectives and chairs the Project Steering Committee |
| PMI / PMBOK | Sponsor | closely related | in PM², also sets the business objectives and chairs the Project Steering Committee |
| PRINCE2 | Executive (PRINCE2) | closely related | Single individual who chairs the Project Board and owns the business case. |
| Six Sigma | Champion | closely related | Often responsible for several improvement projects in an area and tied to tollgates and belt roles. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Project Owner
- Topic area
- Project organization
Distinction
In general usage, the role largely corresponds to the project sponsor or client. Unlike the Project Manager, the Project Owner does not steer day-to-day business; in daily work the Business Manager acts on the Project Owner's behalf. The Solution Provider is the counterpart on the delivering side.
In practice
In the digitalization of grant applications, the head of the funding unit takes on the role of Project Owner. She formulates the objective of halving processing time, accepts the Business Case and chairs the Project Steering Committee. When two departments dispute the priority of their requirements, she decides on the basis of the business objectives and records the decision in the decision log.
Frequently asked questions
Is the Project Owner the same as the Product Owner in Scrum?
No, despite the identical abbreviation. The Product Owner in Scrum is accountable for the Product Backlog and works closely with the team; the Project Owner in PM² is a leadership role on the customer side.
Can the Project Owner delegate tasks?
Yes. The Business Manager represents the Project Owner in the project on a daily basis, for example when preparing the Project Initiation Request. Accountability for project success remains with the Project Owner.
Source and context
- Reference
- PM²-Leitfaden 3.1, Abschnitt 4.5
- Edition
- PM² Guide 3.1
Cite this entry
Project Owner. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/project-owner/
Project Owner (n.d.). PMDecoder, entry on PM²-Leitfaden 3.1, Abschnitt 4.5. https://pmdecoder.com/en/glossary/project-owner/ (retrieved 24 November 2026)
@misc{projectowner,
title = {Project Owner},
note = {PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.5},
url = {https://pmdecoder.com/en/glossary/project-owner/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/project-owner/"> <p>Commissioning role in PM² that sets the business objectives, is accountable for overall success and later takes over the project results</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/project-owner/">Project Owner</a>, PMDecoder, PM²-Leitfaden 3.1, Abschnitt 4.5</footer> </blockquote>
Found a mistake? Let us know, we check every report.