Closing a project
Definition
Closing a project provides PRINCE2 with a fixed end point at which it is checked whether the objectives have been achieved. The process takes place at the end of the final stage, either as planned or prematurely if the Project Board orders the project to stop. The project manager ensures that the products have been accepted and handed over to the operational organization, evaluates the project against its objectives, secures the lessons and makes sure that the review of benefits after the project is planned. Finally, the project manager recommends closure to the Project Board, which confirms it and releases the resources.
Equivalents in other frameworks
Concept Closing stage of a project · five frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PM² | Closing Phase | closely related | fixed phase after the Ready for Closing phase gate, with the Project-End Report |
| Six Sigma | Control phase | closely related | Closes the project, but focuses on securing the improvement for the long term and handing it over to the process owner. |
| general | Project closure | closely related | Process within the final stage rather than a stage of its own; also used for premature closure. |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Closing a project
- Topic area
- Closing
Distinction
The closing phase in PM² and general project closure cover similar tasks. PRINCE2 places closure as a process within the final stage rather than as a stage of its own. Reviewing the benefits, which often arise only later, remains a task for the commissioning organization after the project has ended.
In practice
After a new ticketing system has been introduced in customer service, the project manager hands over the system, documentation and open issues to IT operations. She compares costs and dates with the plan, notes that training started too late and plans a benefits review after six months with the Executive. The Project Board then confirms closure.
Frequently asked questions
How does premature closure work?
Much like planned closure, but with an emphasis on securing completed and partly completed products and recording what is still missing, so that later work can build on it.
Does responsibility for benefits end with project closure?
No. Many benefits arise only after the project. Their review is planned before closure and carried out afterwards by the commissioning organization.
Source and context
- Reference
- PRINCE2 7, Prozesse
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Closing a project. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/closing-a-project/
Hain, D. (n.d.): Closing a project. PMDecoder, entry on PRINCE2 7, Prozesse. https://pmdecoder.com/en/glossary/closing-a-project/ (retrieved 24 November 2026)
@misc{closingaproject,
author = {Hain, Dennis},
title = {Closing a project},
note = {PMDecoder, PRINCE2 7, Prozesse},
url = {https://pmdecoder.com/en/glossary/closing-a-project/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/closing-a-project/"> <p>PRINCE2 process for an orderly end: handing over products, evaluating objectives, securing lessons and recommending closure to the Project Board.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/closing-a-project/">Closing a project</a>, PMDecoder, PRINCE2 7, Prozesse</footer> </blockquote>
Found a mistake? Let us know, we check every report.