Decision tree analysis
also: Decision tree
Definition
In decision tree analysis, a tree starts with a decision from which branches lead to the possible alternatives. At chance nodes, these branch further into possible events with their probabilities. At the end of each path is an outcome, such as cost or profit. Rolling back from the end to the root gives an expected value for each alternative, which makes them comparable.
Equivalents in other frameworks
Concept Evaluating decisions under uncertainty as a tree · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Decision tree analysis | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Decision tree analysis
- Topic area
- Risks and opportunities
Distinction
Expected monetary value is the calculated figure; the decision tree is the representation in which it is determined for multi-stage decisions. An influence diagram shows the relationships between decisions, uncertainties and objectives more compactly, but without all the individual paths. Weighted scoring (Nutzwertanalyse) compares alternatives against several weighted criteria without taking probabilities into account.
In practice
A software company is considering whether to adapt an existing platform for a customer project or to develop a new one. Adaptation costs 200,000 euros, with a 30 per cent probability of an additional 150,000 euros for modifications. New development costs 300,000 euros, with a 20 per cent probability of a further 50,000 euros. The tree gives expected costs of 245,000 euros for adaptation and 310,000 euros for new development. The team opts for adaptation and monitors the modification risk closely.
Frequently asked questions
When is a decision tree suitable?
When a decision has a few clear alternatives whose consequences depend on uncertain events, and probabilities and values can be estimated at least roughly.
Should you always choose the alternative with the best expected value?
Not necessarily. Anyone who cannot bear a large loss may choose an alternative with a worse expected value but a smaller spread.
Source and context
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Decision tree analysis. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/decision-tree-analysis/
Hain, D. (n.d.): Decision tree analysis. PMDecoder. https://pmdecoder.com/en/glossary/decision-tree-analysis/ (retrieved 24 November 2026)
@misc{decisiontreeanalysis,
author = {Hain, Dennis},
title = {Decision tree analysis},
note = {PMDecoder},
url = {https://pmdecoder.com/en/glossary/decision-tree-analysis/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/decision-tree-analysis/"> <p>Method that represents decisions under uncertainty as a branching tree and compares the alternatives by their expected value</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/decision-tree-analysis/">Decision tree analysis</a>, PMDecoder</footer> </blockquote>
Found a mistake? Let us know, we check every report.