Planned value
also: Budgeted cost of work scheduled · abbr. PV, BCWS
Definition
Planned value states how much work, valued at planned cost, was scheduled up to a point in time. It is derived from the time-phased cost plan: adding up the budgets of all work scheduled up to the cut-off date gives the planned value. At the end of the project it equals the total budget. Plotted over time, it forms the planned curve of earned value management.
Equivalents in other frameworks
Concept Budgeted value of planned work · three frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| PMI / PMBOK | Planned value | equivalent | — |
| Scrum | — | no counterpart | — |
| Kanban | — | no counterpart | — |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Planned value
- Topic area
- Monitoring and control
Distinction
Planned value describes what was planned, earned value how much of it was actually achieved, and actual cost what was spent to achieve it. The difference between earned value and planned value is the schedule variance. Planned value should not be equated with a budget in the sense of a spending limit, because it is tied to the timing of the work.
In practice
A municipal utility plans to replace 3,000 electricity meters within six months at 80 euros each. The baseline schedules 1,500 meters for the first three months, so the planned value at that date is 120,000 euros. In fact, 1,200 meters have been replaced. The comparison shows a shortfall of 24,000 euros of planned work, roughly two and a half weeks of work at the planned rate. The utility deploys an additional installation crew.
Frequently asked questions
Where does planned value come from?
From the approved baseline, in which each work package is assigned a budget and a time period.
Does planned value change during the project?
Only if the baseline is reset after an approved change. The project's own delays do not change it.
Source and context
- Reference
- ISO 21506:2024, 3.45
- Edition
- ISO 21506:2024
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Planned value. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/planned-value/
Hain, D. (n.d.): Planned value. PMDecoder, entry on ISO 21506:2024, 3.45. https://pmdecoder.com/en/glossary/planned-value/ (retrieved 24 November 2026)
@misc{plannedvalue,
author = {Hain, Dennis},
title = {Planned value},
note = {PMDecoder, ISO 21506:2024, 3.45},
url = {https://pmdecoder.com/en/glossary/planned-value/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/planned-value/"> <p>Budgeted value of the work that, according to the baseline, should have been completed by a given cut-off date.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/planned-value/">Planned value</a>, PMDecoder, ISO 21506:2024, 3.45</footer> </blockquote>
Found a mistake? Let us know, we check every report.