Network schedule

also: Network diagram

Definition

A network schedule shows which activities or events a project comprises and how they are logically linked. Each path from start to finish represents a chain of work in which each step builds on the one before. Together with the durations, the network schedule allows the earliest and latest dates, the float and the critical path to be calculated. A correct network schedule has exactly one start point and one end point, no loops and no open ends.

Equivalents in other frameworks

Concept Diagram of activities and their dependencies · three frameworks reviewed

Equivalents of Network schedule in other frameworks
FrameworkTerm thereRelationNote
PMI / PMBOKProject schedule network diagramequivalent—
Scrum—no counterpart—
Kanban—no counterpart—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Network schedule

Distinction

The network schedule is the result of network planning techniques. A distinction is made between activity-on-node, activity-on-arrow and event-on-node diagrams. A time-scaled network schedule additionally arranges the nodes along a time axis and thus comes close to a linked bar chart.

In practice

When checking the network schedule for a tunnelling project, the planning software reports two errors: one activity has no successor, and three others form a loop. The open activity is the documentation of the drilling results, which had simply not been linked to the planning approval. The loop arises because planning and review each have the other as predecessor. The team resolves it by entering the revision as a separate activity.

Frequently asked questions

Why are loops not allowed in a network schedule?

Because dates can then no longer be calculated: every activity in the loop would have to finish before itself. Repetitions are shown as separate activities.

What is an open end?

An activity with no predecessor or no successor that is not the start or end of the project. It usually results from forgotten links and distorts the float calculation.

Source and context

Reference
ISO 21506:2024, 3.38
Edition
ISO 21506:2024
Cite this entry
APA

Hain, D. (n.d.). Network schedule. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/network-schedule/

Short form

Hain, D. (n.d.): Network schedule. PMDecoder, entry on ISO 21506:2024, 3.38. https://pmdecoder.com/en/glossary/network-schedule/ (retrieved 24 November 2026)

BibTeX
@misc{networkschedule,
  author  = {Hain, Dennis},
  title   = {Network schedule},
  note    = {PMDecoder, ISO 21506:2024, 3.38},
  url     = {https://pmdecoder.com/en/glossary/network-schedule/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/network-schedule/">
  <p>Graphical representation of a project's activities and their dependencies as a network of nodes and connecting arrows.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/network-schedule/">Network schedule</a>, PMDecoder, ISO 21506:2024, 3.38</footer>
</blockquote>

Found a mistake? Let us know, we check every report.