Communication Management Approach
Definition
The communication management approach describes how a PRINCE2 project communicates with its stakeholders. It builds on an analysis of those involved and affected and records what information they need, who provides it, at what frequency and through which channels. This includes communication within the project organization, such as reports to the project board, and externally, for example to customers, authorities or the public. The approach is created during initiation, becomes part of the project initiation documentation and is reviewed at stage boundaries, because the circle of stakeholders can change over time.
Equivalents in other frameworks
Concept Arrangements for project communication · two frameworks reviewed
| Framework | Term there | Relation | Note |
|---|---|---|---|
| ISO 21506 | Communication plan | closely related | Same purpose; as a management product part of the project initiation documentation and closely linked to the defined reports. |
| PMI / PMBOK | Communications management plan | closely related | additionally covers rules, methods and responsibilities for all communication |
The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.
Classification
- this term
- Communication Management Approach
- Topic area
- Stakeholders and communication
Distinction
The communication plan under ISO 21506 and the PMI communications management plan serve the same purpose. The differences lie in how it is embedded: in PRINCE2 the approach is one management product among others and is closely linked to the defined reports. The reports themselves are separate management products.
In practice
A municipality is refurbishing a main road. The communication management approach provides for residents to be informed by leaflet fourteen days before each closure, for local businesses to attend a monthly round table and for the municipal council to receive a short report each quarter. The project board receives a status report from the project manager every two weeks.
Frequently asked questions
Who prepares the communication management approach?
Usually the project manager, with help from project support. The project board reviews and approves it as part of the project initiation documentation.
Does it need to be adjusted after initiation?
Often, yes. If new stakeholders appear or their expectations change, the approach is revised at the latest when moving into the next stage.
Source and context
- Reference
- PRINCE2 7, Managementprodukte
- Edition
- PRINCE2 7
- Author
- Dennis Hain
Cite this entry
Hain, D. (n.d.). Communication Management Approach. In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/communication-management-approach/
Hain, D. (n.d.): Communication Management Approach. PMDecoder, entry on PRINCE2 7, Managementprodukte. https://pmdecoder.com/en/glossary/communication-management-approach/ (retrieved 24 November 2026)
@misc{communicationmanagementapproach,
author = {Hain, Dennis},
title = {Communication Management Approach},
note = {PMDecoder, PRINCE2 7, Managementprodukte},
url = {https://pmdecoder.com/en/glossary/communication-management-approach/},
urldate = {2026-11-24}
}Embed this definition
HTML fragment for your own website: short definition with source and link, no script and no tracking.
<blockquote cite="https://pmdecoder.com/en/glossary/communication-management-approach/"> <p>PRINCE2 management product defining who, within and around the project, receives which information, when and through which channel.</p> <footer>Source: <a href="https://pmdecoder.com/en/glossary/communication-management-approach/">Communication Management Approach</a>, PMDecoder, PRINCE2 7, Managementprodukte</footer> </blockquote>
Found a mistake? Let us know, we check every report.