Earned value

Definition

Earned value states how much of the approved budget is attributable to the work actually completed by a given data date. Performance is therefore expressed not in hours or percentages but in the same unit as the plan and the costs. Only this makes three figures directly comparable: planned value as the worth of the work scheduled up to the data date, earned value as the worth of the work achieved, and actual cost as what was really spent on it. From these follow the schedule variance (EV − PV), the cost variance (EV − AC) and the indices SPI (EV / PV) and CPI (EV / AC).

Equivalents in other frameworks

Concept Value of work performed · one framework reviewed

Equivalents of Earned value in other frameworks
FrameworkTerm thereRelationNote
ISO 21506Earned valueequivalent—

The circles show how far the meanings overlap: on top of each other equivalent, large overlap closely related, small overlap partially overlapping, separate false friend.

All designations of this concept side by side

Classification

this term
Earned value

Distinction

Earned value under ISO 21506 denotes the same figure. Planned value states what should have been done by the data date and actual cost what the completed work has cost; earned value shows what has actually been achieved. Earned value management is the method that collects and evaluates these figures, earned value only one of its measures. Percent complete feeds into the calculation but is not yet a value in budget terms.

In practice

A school renovation has a budget of 200,000 euros. By the end of the month, work worth 80,000 euros should have been completed according to plan. In fact, work budgeted at 70,000 euros is finished, and 90,000 euros have been spent. The earned value is therefore 70,000 euros. This results in a schedule variance of −10,000 euros, a cost variance of −20,000 euros, an SPI of about 0.88 and a CPI of about 0.78. The project manager then examines the roofer’s change orders, which account for most of the overrun.

Frequently asked questions

How is earned value calculated?

For each work package, the planned budget is multiplied by the percentage of completion achieved; the sum is the earned value of the project. If a work package has a budget of 10,000 euros and is 40 percent complete, its earned value is 4,000 euros.

What is earned value used for?

It makes performance, schedule and cost comparable. Compared with planned value it shows whether the project is on schedule, compared with actual cost whether the work was performed economically. Indicators and forecasts can be derived from this.

How is the percentage of completion determined?

Common methods are fixed rules such as 0/100 (value only on completion) or 50/50 (half the value at the start), crediting achieved intermediate results, or an estimated percentage. The more objective the method, the more meaningful the earned value.

Source and context

Reference
PMI Lexicon of Project Management Terms 4.0 (2024)
Edition
PMBOK Guide – Eighth Edition
Cite this entry
APA

Earned value. (n.d.). In PMDecoder. Retrieved 24 November 2026, from https://pmdecoder.com/en/glossary/earned-value/

Short form

Earned value (n.d.). PMDecoder, entry on PMI Lexicon of Project Management Terms 4.0 (2024). https://pmdecoder.com/en/glossary/earned-value/ (retrieved 24 November 2026)

BibTeX
@misc{earnedvalue,
  title   = {Earned value},
  note    = {PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)},
  url     = {https://pmdecoder.com/en/glossary/earned-value/},
  urldate = {2026-11-24}
}

Embed this definition

HTML fragment for your own website: short definition with source and link, no script and no tracking.

HTML
<blockquote cite="https://pmdecoder.com/en/glossary/earned-value/">
  <p>Budgeted value of all work actually completed up to a given date.</p>
  <footer>Source: <a href="https://pmdecoder.com/en/glossary/earned-value/">Earned value</a>, PMDecoder, PMI Lexicon of Project Management Terms 4.0 (2024)</footer>
</blockquote>

Found a mistake? Let us know, we check every report.